Flexibility market data: the new asset layer

40 min 5 outcomes 3 diagrams + 3 knowledge checks

Flexibility is becoming a first-class GB market, and its data layer is being built right now. Who the assets are, who may dispatch them, and what they actually did are three separate datasets, each with its own owner, and none of them existed in usable national form five years ago.

By the end of this module you will be able to:

  • Describe the market facilitator role and what FMAR registers
  • Explain primacy between NESO and DNO dispatch, and read a primacy conflict
  • Use the Embedded Capacity Register to profile a local network
  • State what replaced STOR, Fast Reserve and the old reserve products
  • Describe the 2026 Demand Flexibility Service design and its data consequences

1 April 2026, 05:00: STOR ended after two decades, replaced by Slow Reserve

At 05:00 on 1 April 2026 the Short Term Operating Reserve stopped accepting instructions for the last time. STOR had been part of the GB reserve landscape for around twenty years. It was the product that diesel peaking sets, standby generators and, later, aggregated demand-side portfolios were built around. Its replacement, , had already been running since March 2025, so the handover was a fade rather than a cliff edge.

For a provider, the day STOR ended was not a market event. It was a data migration. The asset had to be re-registered against a new product, the availability declarations moved to a different schema, the settlement references changed, and the internal dashboards that had reported STOR availability for a decade stopped resolving. That is the pattern this whole module teaches: in flexibility, a product change is always a schema change, and the organisation that survives it is the one whose asset data was accurate before the change was announced.

19.1 The market facilitator and the asset register

Registration data is the precondition for stacked flexibility revenues. That single sentence explains why Great Britain has spent the last two years building institutions whose only product is a register.

Start with the problem. A battery sitting behind a distribution connection can, in principle, earn from several places at once: a flexibility tender to defer a local reinforcement, a reserve product, the , and wholesale trading. Each of those buyers historically ran its own onboarding: its own forms, its own technical evidence, its own identifiers, its own view of what the asset was. A 10 MW battery could exist as four different records in four different systems, with no guarantee that the capacity figures agreed. For a large developer that was an overhead. For a 200 kW site with one part-time analyst it was a barrier to entry, and the small sites are precisely where most of the untapped flexibility sits.

Ofgem's answer has two parts, and it is worth keeping them separate because they are often conflated. The first is an institution. In July 2024 Ofgem appointed as the GB , an independent coordinator for distributed flexibility markets. The policy framework decision that defines the role followed in June 2025, and the facilitator began operating from early 2026. Its job is coordination rather than dispatch: standardising how flexibility markets describe themselves, publishing common definitions and processes, and making it possible for a small provider to find the revenue routes available to a given asset in a given place without reading fourteen separate procurement handbooks.

The second part is a dataset. stands for Flexibility Market Asset Registration. It is an Ofgem programme, not an Elexon product, although Elexon was appointed delivery body on 7 March 2025. Ofgem confirmed the design in its March 2025 decision, and the register is due to launch in 2027. The principle is register once, participate many times: an asset owner records the asset and its technical characteristics in one national place, and every flexibility market that needs to know about that asset reads the same record.

The market facilitator sits between the flexibility markets and the asset registers

The same standards arrow rises into both the national and the local market, so an asset registered once can be offered to either, which the per-network registers of today cannot support and the one-stop register is meant to.

Elexon, the market facilitator, sits between the flexibility markets and the asset registers. Source: Ofgem market facilitator framework decision, Ofgem FMAR decision, ENWL Embedded Capacity Register.

The market facilitator sits between the flexibility markets and the asset registers Ecosystem map in three bands. A red strip at the top names the Ofgem market facilitator policy framework decision of June 2025. The markets band holds two cards, NESO national services and DSO local flexibility markets. The emphasised centre card names Elexon as market facilitator, appointed July 2024 and operating from early 2026, with arrows labelled common standards rising into both market cards. The registers band holds the FMAR one-stop asset register launching 2027, reached by an arrow labelled delivery body dated 7 March 2025, beside the per-DNO Embedded Capacity Register, the public record today. A closing strip reads register once, stack revenues across markets. OFGEM · MARKET FACILITATOR POLICY FRAMEWORK Decision June 2025 MARKETS REGISTERS NATIONAL NESO NESO national services Reserve services and the Balancing Mechanism LOCAL DSOs DSO local flexibility markets Local constraint services procured by DNOs MARKET FACILITATOR Ofgem appointed Elexon Appointed July 2024, operating from early 2026 One rulebook so an asset can serve many markets FROM 2027 Ofgem · Elexon FMAR one-stop asset register Flexibility Market Asset Registration One-stop register, launches 2027 TODAY Per DNO Embedded Capacity Register Public record of distribution-connected resources common standards common standards delivery body, 7 Mar 2025 REGISTER ONCE, STACK REVENUES ACROSS MARKETS

Read the map with the settlement chain from stage 2 in mind. The facilitator sits between the markets and the registers. It does not buy flexibility and it does not instruct assets. It shapes the common language those transactions are expressed in, and FMAR supplies the reference data that language points at. The relationship to settlement is the useful analogy: Elexon does not trade electricity either, but every trade eventually has to reconcile against the records Elexon holds.

Note what FMAR is not. It is not a market, so nothing is bought or sold through it. It is not a dispatch platform, so no instruction is issued from it. It is not a performance record, so it does not tell you what an asset delivered last winter. It is the identity and capability layer, and the reason that matters is stacking. Revenue stacking is only safe when every buyer can see the same asset, the same connection point and the same capacity, because otherwise the same megawatt gets promised twice. That problem is exactly what section 19.2 is about.

Check your understanding

What does FMAR stand for, and what does it actually hold?

19.2 Who dispatches: primacy

When the national system operator and a local network both want the same asset at the same moment, one of them has to give way, and the rules that decide which one are called . The ENA Open Networks programme publishes the primacy rules framework that GB operates to.

The conflict is structural rather than accidental. NESO buys flexibility to balance the national system: it is solving a frequency or a national margin problem, and it does not much care where in the country the response comes from. A buys flexibility to manage a specific piece of local network: it needs the response at that substation, on that feeder, or the service is worthless. The same battery can satisfy both needs, so both will contract with it, and on a small number of days both will want it in the same half hour. Sometimes the two instructions are compatible. Sometimes they point in opposite directions, and importing to relieve a national surplus while the local network needs you to stop importing is a genuine physical contradiction.

Primacy resolves that in advance rather than in the moment. The framework establishes which need takes precedence in defined circumstances, and just as importantly it establishes what the two parties must tell each other and when. That second half is the data engineering. A primacy rule that nobody can operationalise is a policy document. A primacy rule with an agreed conflict notification, an agreed identifier for the contested asset and an agreed time window is a working control.

Who dispatches the asset: NESO and DSO routes meet the primacy gate

Both routes are valid contracts, so the gate is not correcting an error: the primacy rules pick which instruction proceeds, the other stands down, and the clash itself is written down as data the market can audit later.

When NESO and DSO instructions meet at one asset, the ENA primacy rules decide which proceeds, and the conflict itself becomes data. Source: ENA Open Networks primacy rules.

Who dispatches the asset: NESO and DSO routes meet the primacy gate Gate board in four rows. Two route cards at the top show NESO instructing the asset through the Balancing Mechanism, reserve services and the DFS, and the DSO instructing the same asset through local flexibility and constraint contracts. Arrows labelled national instruction and local instruction drop into the emphasised gate card, two instructions, one asset, in the same window. An arrow labelled rules applied leads to the outcome card: the ENA primacy rules decide, one instruction proceeds, the other stands down, and the conflict is itself recorded as data. A red strip names the ENA Open Networks primacy rules. NESO ROUTE National NESO instructs the asset Balancing Mechanism, reserve services, DFS DSO ROUTE Local The DSO instructs the asset Local flexibility and constraint contracts THE GATE Same window Two instructions, one asset Both services are contracted and both calls are valid PRIMACY ENA Open Networks The primacy rules decide One instruction proceeds, the other stands down The conflict is itself recorded as data national instruction local instruction rules applied ENA OPEN NETWORKS · PRIMACY RULES FOR NESO AND DSO DISPATCH

In practice, conflict data has a recognisable shape. There is an asset identity, which is the reason FMAR is the enabling condition for everything else in this module. There is a location, expressed against a network connection point rather than a postcode, because the network cares about topology. There is a contracted window, which is the period each buyer has bought availability for. There is a service type, so the parties can tell whether the two requirements are physically compatible or mutually exclusive. And there is an outcome record, which says who took the asset and what the other buyer did instead.

Two scenarios are worth holding in your head. In the first, a DSO has contracted a battery to hold a feeder within limits during a planned outage, and NESO wants the same battery for a national reserve requirement in the same window. The local need is specific, physically located and cannot be met from elsewhere. In the second, an aggregator has offered the same portfolio of domestic assets into both a local flexibility tender and a national service without telling either buyer, which is not a primacy conflict at all. It is a registration failure, and it is the failure mode a single asset register exists to make visible.

The takeaway for a data professional is that primacy turns an institutional relationship into a schema. Every clause in the framework has to become a field that somebody populates, on a timescale short enough to matter, or the rule does not bind anything.

Check your understanding

A DSO has contracted a distribution-connected battery for a specific feeder constraint during a planned outage. NESO wants the same battery in the same half hour for a national reserve requirement. What kind of problem is this, and what resolves it?

19.3 The reserve shake-up

Every product change is a data schema change for providers. Between 2024 and 2026 GB replaced most of its reserve product set, and a provider who tracked only the market headlines and not the schema consequences spent that period repeatedly discovering that yesterday's integration no longer submitted anything.

Take the replacements in order. went live in March 2024, providing NESO with headroom procured ahead of the Balancing Mechanism. arrived in phase 1 in December 2024 and phase 2 in September 2025, taking over from Fast Reserve. Slow Reserve went live in March 2025 and took over from STOR, which ran on in parallel until it ended at 05:00 on 1 April 2026. The old names are gone: STOR and Fast Reserve are retired products, and any document, dashboard or course that still teaches them as live is describing a system that no longer exists.

Reserve replacement map: STOR, Fast Reserve and the products that replaced them

Two of the three rows are replacements and the third has nothing on its outgoing side, so a provider following these products faced two migrations and one new registration, each of them a change to the data it must submit.

Quick Reserve and Slow Reserve replaced Fast Reserve and STOR, and Balancing Reserve arrived new in 2024. Source: NESO Quick Reserve and Slow Reserve service pages.

Reserve replacement map: STOR, Fast Reserve and the products that replaced them Replacement timeline in three rows, outgoing products on the left and current products on the right. Row one: no predecessor, marked with a dashed outline, leads to Balancing Reserve, live since 2024, via an arrow labelled new for 2024. Row two: Fast Reserve, retired, leads to Quick Reserve, phase 1 December 2024 and phase 2 September 2025, via an arrow labelled replaced by. Row three: STOR, Short Term Operating Reserve, which ended at 05:00 on 1 April 2026, leads to Slow Reserve via an arrow labelled replaced by. A closing strip states that every product change is a data schema change for providers. NESO RESERVE PRODUCTS · THE 2024 TO 2026 SHAKE-UP OUTGOING CURRENT NO PREDECESSOR Nothing retired A new product, not a swap RETIRED Fast Reserve Predecessor to Quick Reserve RETIRED STOR Short Term Operating Reserve Ended 05:00, 1 April 2026 LIVE NESO Balancing Reserve Live since 2024 LIVE NESO Quick Reserve Phase 1 December 2024 Phase 2 September 2025 LIVE NESO Slow Reserve In place of STOR since 1 April 2026 new for 2024 replaced by replaced by EVERY PRODUCT CHANGE IS A DATA SCHEMA CHANGE FOR PROVIDERS

The has followed the same direction of travel, from an emergency measure to a standing part of the toolkit. DFS became a year-round NESO service on 27 November 2024, which ended the assumption that consumer flexibility is a winter product to be stood up in November and packed away in March. On 9 April 2026 it went further: the service became bi-directional and zonal, with a participation threshold of 0.1 MW.

Unpack those three words, because each is a data consequence. Bi-directional means the service can call for consumption to go up as well as down, so a provider's baseline and performance calculation has to work in both directions, and the sign conventions in every downstream report have to be right. Zonal means location now carries value, so a portfolio has to be resolvable to a zone rather than treated as an undifferentiated national block, which pushes location data quality from a nice to have into a settlement input. The 0.1 MW threshold sets the floor for participation, which shapes how small an aggregated portfolio can usefully be and therefore how much per-site data a provider has to manage to reach it.

Underneath all of this sits the metering evidence, which is where this module leans on stage 2. A flexibility service is paid on what an asset demonstrably did against a baseline, and the demonstration comes from half-hourly data that has to be good enough to survive scrutiny. As migration completes, the same actual half-hourly reads that settle the market are the reads a flexibility performance claim rests on, which raises the evidentiary bar and removes some of the estimation arguments that used to be available on both sides.

Common misconception

STOR is the standard GB reserve product, activated within a few hours of instruction.

STOR ended at 05:00 on 1 April 2026 after roughly two decades. Slow Reserve, live since March 2025, replaced it. Fast Reserve was replaced by Quick Reserve, phase 1 in December 2024 and phase 2 in September 2025, and Balancing Reserve has been live since March 2024. Reserve product names carry contract terms and data schemas with them, so using a retired name in a specification points integrations at services that no longer accept submissions.

Check your understanding

Which mapping of old reserve products to their replacements is correct?

19.4 Reading the registers

FMAR launches in 2027. Until then, the best public record of what is already connected to the distribution networks is the , and learning to read one is the most directly employable skill in this module.

Each DNO publishes an ECR listing distribution-connected generation and storage above a size threshold, with the connection point, the capacity and the status of the connection. Electricity North West's register is a good worked example because its structure is typical. The register answers the first question anybody asks about a locality: what is already there. Before you model a flexibility opportunity, before you site a battery, and before you believe a claim about how much distributed resource a region holds, the ECR is where you check.

It is also worth being honest about its limits, because a register is only as useful as your understanding of what it excludes. An ECR records connected and contracted capacity, not what an asset is contracted to deliver into any flexibility market, and not what it actually delivered. Capacity below the publication threshold does not appear, which is most domestic solar. Registers are refreshed on a publication cycle rather than continuously, so a very recent connection may not be visible. And each DNO publishes independently, which means field names, categories and status vocabularies vary across the six DNO groups that publish them. Anyone building a national view is doing a reconciliation job first and an analysis job second, which is precisely the pain FMAR is meant to remove.

Storage co-location is the sharpest data edge case in this area, and it is worth working through slowly because it catches people who have understood everything else. Put a battery and a solar array behind the same connection, and the question of what the meter is telling you gets hard. From stage 1 you already know that import and export sit on separate registers, and that the import register never goes negative. Applied here, that means a single site-level flow figure cannot by itself tell you whether the battery discharged, the solar generated, or the site simply consumed less. Whether a co-located battery's charging is drawn from the array or from the grid changes the commercial and regulatory treatment, and separating those two things demands metering arrangements that resolve the components rather than only the net. The teaching point generalises: as more assets co-locate, net site data stops being sufficient evidence, and the flexibility market's appetite for component-level measurement grows accordingly.

Put the module together and you have the shape of a local flexibility brief, which is the deliverable this material is really preparing you to write. Such a brief needs the network context, meaning what is already connected in the area and where the network is constrained, taken from the ECR and the DNO's network development and publications. It needs the revenue routes, meaning which national and local products the asset could serve and what each one now requires, which is the reserve and DFS picture from section 19.3. It needs the dispatch question answered, meaning how primacy would resolve a clash between the local and national buyer, from section 19.2. It needs the registration position, meaning what the asset is currently recorded as and what FMAR will require of it from 2027. And it needs an honest statement of the evidence, meaning what the metering can actually demonstrate, which is where co-location and half-hourly data quality decide whether the numbers in the brief will survive contact with a counterparty.

Core distinctions

  • Elexon was appointed GB market facilitator in July 2024, with Ofgem's policy framework decision in June 2025 and operations from early 2026. The role coordinates distributed flexibility markets; it does not buy or dispatch flexibility.
  • FMAR is Flexibility Market Asset Registration, an Ofgem programme with Elexon appointed delivery body on 7 March 2025, delivering a one-stop flexibility asset register launching in 2027. Registration data is the precondition for stacked revenues.
  • Primacy, set out in the ENA Open Networks framework, decides who has first call when NESO and a DSO want the same asset in the same window. Every clause of it becomes a data field somebody has to populate in time to matter.
  • The reserve set was rebuilt: Balancing Reserve live March 2024, Quick Reserve replacing Fast Reserve (phase 1 December 2024, phase 2 September 2025), Slow Reserve replacing STOR from March 2025, and STOR ending at 05:00 on 1 April 2026.
  • DFS has been year-round since 27 November 2024 and became bi-directional and zonal with a 0.1 MW threshold on 9 April 2026. Bi-directional changes sign conventions, zonal makes location a settlement input, and the threshold sets the floor for portfolio size.
  • The Embedded Capacity Register is the public record of distribution-connected resource today, but it records capacity rather than contracted or delivered flexibility, varies by DNO, and cannot resolve co-located storage from net site flow.

Standards and sources cited in this module

  1. Ofgem, Market facilitator policy framework decision

    June 2025

    Defines the market facilitator role that Elexon was appointed to in July 2024, and the coordination functions described in section 19.1.

  2. Ofgem, Flexibility Market Asset Registration decision

    March 2025

    The decision that confirms FMAR's design, names Elexon as delivery body and sets the 2027 register launch. It is the authority for the expansion Flexibility Market Asset Registration.

  3. Elexon, appointed as Flexibility Market Asset Registration delivery body

    7 March 2025

    Confirms the delivery body appointment date used in section 19.1 and sets out what Elexon has been asked to build.

  4. Energy Networks Association, Open Networks primacy rules framework

    Version 3

    The published framework behind section 19.2, covering how NESO and DSO dispatch conflicts are resolved and what the parties must exchange.

  5. NESO, Slow Reserve

    Reserve services

    Primary source for Slow Reserve replacing STOR and for STOR ending at 05:00 on 1 April 2026, the event in this module's opening story.

  6. NESO, Quick Reserve

    Reserve services

    Primary source for Quick Reserve replacing Fast Reserve, with phase 1 in December 2024 and phase 2 in September 2025.

  7. NESO, Demand Flexibility Service

    Service design and participation requirements

    Source for DFS becoming year-round on 27 November 2024 and for the bi-directional, zonal design with a 0.1 MW threshold from 9 April 2026.

  8. Electricity North West, Embedded Capacity Register

    Network information

    A worked example of the ECR structure used in section 19.4, showing the fields a local flexibility brief starts from.

Practice and Strategy · Energy System Data