Voltage

Holding voltage within statutory limits at every tier.

The GB grid has six voltage levels, each with a nominal and a statutory operating range. Voltage must stay within its range during normal operation and recover within defined times after a fault. NESO procures reactive power to keep transmission voltages in band. DNOs manage distribution voltage. Voltage constraints, not thermal limits, are now often the binding factor on new connections in parts of Scotland and the South East.

11Route 11 of 12 · Operations and networks
11 min read 4 sections 2 diagrams 1 decision tool Last verified

After this route you will be able to

  • Name the six GB nominal voltage levels and their statutory tolerance bands.
  • Explain what reactive power does and why it matters for voltage.
  • Describe how voltage and thermal constraints differ as connection-limiting factors.
  • Identify the NESO reactive power products (Obligatory, Enhanced, Voltage-only).
  • Make a reasoned call on voltage-constrained connection treatment.
Outdoor 275 kV substation with reactive power compensation equipment

14 July 2022Scotland voltage constraint · £200m in constraint payments

Scotland's 400 kV network could not voltage-support all its generation at once. NESO paid wind farms to turn off.

On a breezy summer afternoon in July 2022, Scottish wind output exceeded the ability of the Scottish transmission system to export the power south while holding voltage in statutory limits. NESO paid Scottish wind farms to reduce output and paid gas generators in England to increase output. The week's constraint cost reached £200 million.

The physics is subtle. Thermally, the lines had capacity. Voltage-wise, long 400 kV circuits carrying high power develop voltage rise at the receiving end and voltage droop at the sending end. Without reactive power compensation, voltage drifts out of its statutory band and the lines must be de-rated.

The 2022 constraint pattern became routine in 2023 and 2024. Scottish wind now regularly outstrips the ability of the transmission system to deliver it to England within voltage bounds. The response is a queue of reinforcement projects (ASTI programme, £58 bn to 2035) plus tactical fixes: synchronous condensers, SVCs, STATCOMs.

The grid has enough thermal capacity. Why is voltage the binding constraint, and what does that tell us about where to put the next billion pounds of reinforcement?

The answer starts with the voltage tiers and their statutory limits. Each tier carries a different tolerance; each tolerance is set in a specific standard.

Section 01 · Voltage tiers and limits

Six nominals, six operating bands.

GB voltage levels follow IEC 60038. The statutory operating ranges are set in the Grid Code (transmission) and the Electricity Safety, Quality and Continuity Regulations (distribution).

Diagram 01 · GB voltage tiers and operating bands
Tier
Nominal
Steady-state range
Fault recovery
Standard
Super grid
400 kV
±5 %
400 ms to 85 % nominal
Grid Code CC.6
Sub-transmission
275 kV
±10 %
400 ms to 85 %
Grid Code CC.6
Regional transmission
132 kV
±10 %
400 ms to 85 %
Grid Code CC.6
Primary distribution
33 kV
±6 %
5 s to 90 %
ESQCR 2002
Secondary distribution
11 kV
±6 %
5 s to 90 %
ESQCR 2002
Low voltage
230 V
+10 % / -6 %
60 s to 90 %
ESQCR 2002 / BS EN 50160

LV asymmetric range (+10 %, -6 %) reflects the practical reality of residential installations. BS EN 50160 adds 10-minute average and rapid voltage change limits that apply alongside ESQCR.

Section 02 · Reactive power

Reactive power is the lever. Three NESO products procure it.

Reactive power (measured in VAr or var, MVAr, GVAr) is the component of electrical power that maintains voltage. It does no useful work at the load but is essential for the system to hold voltage within its band.

Generators, capacitor banks, STATCOMs, SVCs and synchronous condensers all produce or absorb reactive power. NESO procures three related products on the transmission system.

Obligatory Reactive Power Service (ORPS) is what every transmission-connected generator above a threshold must provide as part of its connection contract. It is paid at a regulated tariff.

Enhanced Reactive Power Service (ERPS) is additional capability beyond ORPS, tendered for in specific locations where NESO needs more voltage support than obligatory contributions deliver.

Voltage-only services (including synchronous condensers) provide voltage support without active power capability. Since 2020 NESO has contracted synchronous condensers at three sites to replace some of the inertia and voltage support that departing thermal plants used to provide.

Each Large Power Station and Embedded Large Power Station connected to the Transmission System shall be capable of continuously supplying full rated reactive power at any voltage between 95 % and 105 % of Nominal System Voltage.

Grid Code CC.6.3.2 (reactive capability)

Section 03 · Voltage-constrained connections

Reinforce, install STATCOMs, or flex the connection?

When a proposed connection is blocked by voltage rather than thermal capacity, there are three responses. Each has different cost and timeline.

Three options, different costs and timelines. Reinforce the transmission node. Build capacity. Install STATCOM. Buy reactive capability locally. Flexible connection. Constrain at times of high voltage. This is the ASTI answer. It is the right long-run fix but too slow for a 2028 connection request. Start over This is the tactical answer. STATCOMs are now a standard NESO tool. Works well for voltage constraint, not thermal. Start over This is the fastest and cheapest option. It commercialises the voltage constraint rather than fixing it. Many 2025 grid-scale batteries operate on flexible connections. Start over

Check your understanding

Three questions on what you have just read.

±5 percent ±10 percent +10 %, -6 % ±6 percent Provides mechanical inertia Generates active power Injects or absorbs reactive power to hold voltage Stores electricity electrochemically ~£500 m ~£2.0 bn ~£5 bn ~£10 bn

Key takeaways

  • Six voltage tiers, each with a statutory steady-state band and fault-recovery requirement.
  • Reactive power holds voltage. NESO procures it through Obligatory, Enhanced, and Voltage-only services.
  • Voltage, not thermal, is often the binding constraint on new connections in Scotland and South East.
  • STATCOMs and synchronous condensers are tactical fixes; ASTI reinforcement is the long-run answer.
  • 2024 constraint costs were ~£2 bn, mostly paying Scottish wind to reduce output while southern gas filled in.

References

  1. NESO: Grid Code CC.6 (voltage)

    Statutory voltage ranges and reactive capability.

    Primary statutory reference.

  2. Electricity Safety, Quality and Continuity Regulations 2002

    Distribution voltage tolerance bands.

    Statutory distribution reference.

  3. NESO: Reactive power services

    ORPS, ERPS, voltage-only service specifications.

    Operational procurement reference.

  4. Ofgem: Accelerated Strategic Transmission Investment (ASTI)

    £58 bn programme for transmission reinforcement to 2035.

    Long-run reinforcement programme source.

The next route covers connections. Where voltage, thermal and queue reform combine into the practical question of how and when a new generator gets connected.