The Great Britain electricity connections queue after Connections Reform, with the Gate 2 outcomes of April 2026

This note sets out what the connections queue looks like in May 2026, six weeks after NESO published the Gate 2 detailed results and twelve months after the Ofgem Connections Reform decision of April 2025 swept aside the first come, first served regime that had built a 722 gigawatt contracted backlog by Q4 2024. The reform chain runs Connections Reform decision, Connections Network Design Methodology (30 April 2025), Gate 2 Criteria Methodology, Gate 2 to Whole Queue process. The eight Gate 2 criteria in S18 of the CNDM are the test that a project either meets or does not. The April 2026 outcomes ranked 283 gigawatts of generation and storage and 99 gigawatts of demand into Phase 1 (target 2030) and Phase 2 (target 2035), with offer-issuance windows running March to November 2026 and the next application window in H2 2026. A worked example at the end takes a hypothetical 100 megawatt battery project from initial enquiry through the TM04+ filter, the CNDM zonal map, the eight criteria check, the firm-offer issuance, and energisation.

Last verified 28 May 2026

Sources and standards

Every reform date, queue-volume figure, and gate criterion resolves to a primary instrument: the Ofgem Connections Reform decision letter, the NESO Connections Network Design Methodology (CNDM) of 30 April 2025, the Gate 2 Criteria Methodology (G2CM), the NESO Gate 2 detailed results of April 2026, or one of the underlying statutes (Electricity Act 1989, Energy Act 2023). Where a numerical claim sits behind a methodology table, the relevant section number is given inline (S18 CNDM section reference, G2CM criterion number).

Where connections reform stands in May 2026

The Gate 2 detailed results published by NESO in April 2026 are the first end-to-end picture of what the reformed queue looks like.13 Across generation and storage, 283 gigawatts have been progressed to firm offers; across demand connections, 99 gigawatts. The portfolio is sorted into two phases. Phase 1 covers the projects that NESO and Ofgem judge are needed and capable of energising by 2030 to meet the Clean Power 2030 target. Phase 2 covers projects that are needed but on a 2035 horizon. Offer-issuance windows run from March 2026 through to November 2026, in sequenced tranches by technology and connection voltage. The next application window opens in the second half of 2026; the precise dates are still being finalised through the open-governance process under the CUSC and DCUSA modification panels.

Behind those headline numbers sits a regime that did not exist eighteen months ago. The Ofgem Connections Reform decision of April 2025 approved the package that retired the legacy first come, first served model.7 NESO then published three methodologies in close succession. The Connections Network Design Methodology (CNDM, 30 April 2025) defines how the network is designed against a firm pipeline rather than against a speculative backlog. The Gate 2 Criteria Methodology (G2CM) sets the eight tests a project has to meet to receive a firm Gate 2 position. The Gate 2 to Whole Queue process spells out how legacy projects without Gate 2 status are handled, including the orderly withdrawal of offers that no longer fit the strategic network plan. The reform sits on top of the duty to offer terms in section 16 of the Electricity Act 1989, and the queue-management duty that NESO inherited from the former ESO under Part 5 of the Energy Act 2023.11

What changed in practice. A project that lodged a CUSC application in 2022 used to receive an indicative connection date based on its position in the contracted-queue order, often a year in the late 2030s. A project lodging in May 2026 lands in a structured assessment against the eight criteria, with a firm Phase 1 date if it qualifies and a firm Phase 2 date if it is needed on the longer horizon. Projects that lodged before the reform and did not progress through the Gate 2 to Whole Queue assessment have been moved to a withdrawal track, freeing the entry capacity their offers had locked up against the network model. The Centralised Strategic Network Plan methodology approved by Ofgem in April 2026 then drives the network build-out that those Phase 1 and Phase 2 connections need, on a three-year cycle that replaces the older Network Options Assessment.12 The Capacity Market T-4 auction in February 2026 cleared 40.1 gigawatts for delivery 2029/30 against a 39.4 gigawatt target, which gives the connections queue a parallel revenue anchor for the projects that need it.8 The LTDS Stage 2 publication on 29 May 2026, under the Ofgem derogation letter of 13 May 2026, is the network model the queue is now being designed against; the visibility of the constraints under voltage rise and thermal headroom is the most current it has ever been.1

A project journey from initial enquiry to energisation through the reformed Great Britain connections queue in 2026

Based on the NESO Connections Network Design Methodology of 30 April 2025 and the Gate 2 detailed results of April 2026, the diagram sets out the seven stages a project moves through under the reformed regime.7 13 Each stage carries an indicative timescale; the timescales are the working assumptions a developer should plan against rather than statutory floors.

A seven-stage queue walk from initial enquiry through TM04+ filter, CNDM zonal placement, the eight Gate 2 criteria, firm-offer issuance, construction and energisation A horizontal sequence of seven stages reading left to right. Stage 1 is the initial enquiry and CUSC application at month zero. Stage 2 is the TM04+ filter that retires legacy speculative positions. Stage 3 is the CNDM zonal placement where the project is sited against the Strategic Spatial Energy Plan and the Centralised Strategic Network Plan. Stage 4 is the Gate 2 Criteria Methodology assessment against eight criteria. Stage 5 is the firm-offer issuance within the March to November 2026 window for the current cycle. Stage 6 is construction under the Bilateral Connection Agreement with milestone reporting. Stage 7 is energisation and final operational notification. Each stage box names its owner and its timescale. Arrows connect the stages left to right. Two side branches indicate the off-ramps where a project either withdraws under the Gate 2 to Whole Queue process or is re-routed to a flexibility contract under Active Network Management. 1. Initial enquiry Developer to NESO (transmission) or DNO (distribution). Month 0 2. TM04+ filter Readiness and data quality check; legacy queue retired. Month 0 to 2 3. CNDM placement Zonal map against SSEP and CSNP. Month 2 to 4 4. Eight criteria G2CM assessment across the eight tests in S18. Month 4 to 6 5. Firm offer BCA issued in the March to November 2026 window. Month 6 to 8 6. Construction Schedule 11 milestone reporting to NESO and DNO. 2 to 4 years 7. Energise Final Operational Notification under Grid Code CC.6. Phase 1 to 2030 Off-ramp A: Gate 2 to Whole Queue orderly withdrawal of legacy offer Off-ramp B: flexibility under ANM faster connection with curtailment terms Reading the stages Stage 1 is owned by the applicant; the application drops into the CUSC track at transmission or the DCUSA track at distribution. Stages 2 to 4 sit with NESO under the Connections Network Design Methodology and the Gate 2 Criteria Methodology. Stage 5 is the firm Bilateral Connection Agreement; the offer carries a Phase 1 date for 2030 delivery or a Phase 2 date for 2035. Stage 6 runs Schedule 11 milestone reporting; missing two consecutive milestones triggers a cure-or-terminate notice. Stage 7 is energisation against Grid Code CC.6 or Distribution Code DPC4, ending in the Final Operational Notification.

The seven stages above are the working sequence under the reformed regime; pre-reform applications passed through far fewer formal gates and waited far longer between them. The off-ramps are part of the design: the Gate 2 to Whole Queue process is what allows the legacy backlog to be reduced in an orderly manner, and the flexibility off-ramp is what allows a project to accept curtailment terms in exchange for an earlier energisation date when the local network does not yet have firm headroom.

The reform chain from April 2025 to April 2026

The reform package is a chain of instruments, not a single document. The chain starts with the Ofgem Connections Reform decision letter of April 2025, which approved the policy direction and authorised NESO to publish the methodologies that operationalise it.7 The decision sits under the Electricity Act 1989 section 6 licence regime (transmission, distribution, generation, supply) and the queue-management duty transferred to NESO under Part 5 of the Energy Act 2023.11 The decision did not amend the section 16 duty to offer terms; what it changed is the rules NESO follows in framing the offer.

The Connections Network Design Methodology (30 April 2025)

The CNDM is the spatial and engineering document of the reform package. It defines how NESO designs the network against a firm pipeline rather than against the whole contracted queue. It introduces zonal capacity envelopes aligned to the Strategic Spatial Energy Plan (SSEP) methodology of May 2025 and to the Centralised Strategic Network Plan, the methodology for which was approved by Ofgem in April 2026.12 A project lodging an application after 30 April 2025 is placed against the CNDM zonal map and the resulting capacity envelope, not against the older first come, first served order. Section 18 of the CNDM names the eight criteria a project has to meet to qualify for Gate 2 status; those criteria are set out in detail in the dedicated Gate 2 Criteria Methodology and are reproduced in the section below.

The Gate 2 Criteria Methodology (G2CM)

The G2CM is the procedural document. It defines the assessment process NESO follows when sorting an application against the eight criteria, the evidence the applicant has to provide for each criterion, and the score weighting and pass thresholds. The G2CM also sets the cadence of application windows and the firm-offer issuance windows that follow. The first issuance window under the reformed regime opened in March 2026 and runs through to November 2026, with batches sequenced by technology and connection voltage. The G2CM is the document a developer working on a new application reads first; it tells them what evidence the team needs to assemble and on what schedule.

The Gate 2 to Whole Queue process

The Gate 2 to Whole Queue process handles the legacy. By Q4 2024 the contracted transmission queue had reached approximately 722 gigawatts. The Gate 2 to Whole Queue process applies the same eight criteria to projects that lodged applications before April 2025, identifying which legacy projects qualify for Phase 1 or Phase 2 Gate 2 status and which are retired through an orderly withdrawal of the offer. The retired projects free up the entry capacity their offers had locked up, which is the mechanism that brought the post-reform queue down from 722 gigawatts to a structured 283 gigawatts generation and storage plus 99 gigawatts demand.13 The licence condition that holds NESO and the DNOs to publishing the network model the reform is being run against is SLC 25 of the Electricity Distribution Licence and the parallel transmission licence condition; SLC 25.2 sets the cycle at intervals of not more than seven years, and the LTDS Stage 2 publication of 29 May 2026 is the most recent step in that cycle.10

DateInstrumentWhat it does
April 2025Ofgem Connections Reform decision letterApproves the reform package and authorises NESO to publish the methodologies that follow.
30 April 2025CNDM (Connections Network Design Methodology)Defines the zonal placement of new connections against the SSEP and CSNP envelopes; section 18 names the eight Gate 2 criteria.
May 2025SSEP Methodology v.1Sets the strategic spatial framework the CNDM aligns to; pathway options due to Secretary of State summer 2026.
2025Gate 2 Criteria Methodology (G2CM)Defines the procedural assessment against the eight criteria, evidence requirements, and pass thresholds.
2025 to 2026Gate 2 to Whole Queue processApplies the eight criteria to legacy queue positions; orderly withdrawal of offers that no longer fit the strategic plan.
April 2026Gate 2 detailed results (NESO)283 GW generation and storage and 99 GW demand progressed; Phase 1 to 2030; Phase 2 to 2035.13
April 2026CSNP Methodology Approval Decision (Ofgem)Approves the network plan methodology against which the connections phasing is co-ordinated; T-CSNP due June 2026.12
13 May 2026LTDS CIM Stage 2 and 3 Extension Derogation LetterApproves the Stage 2 model the reformed queue is now being designed against.1
29 May 2026LTDS Stage 2 publicationThe network model a developer can plan a new application against in the H2 2026 window.

The chain reads forwards as policy then methodology then results. A developer who walks the chain backwards from the Gate 2 detailed results gets a precise picture of what the reformed regime is asking them to evidence, and on what schedule.

The queue before and after TM04+

Setting the before and after side by side makes the reform easier to read. The headline numbers are stark, but the more important contrast is in the mechanics. Before TM04+, the queue ordered applicants by the date their CUSC-compliant or DCUSA-compliant application landed. A 2 megawatt rooftop solar project sat ahead of a 2 gigawatt offshore wind farm with full development consent if the rooftop application arrived first. The position carried a firm date, and a developer could trade the position by selling the project company. The connection date the position implied was often more than a decade in the future even for small, ready, well-sited projects, because the position depended on the speculative pipeline ahead of it that had no obligation to build.

After TM04+, the position depends on the readiness of the project against the eight Gate 2 criteria and on its fit with the zonal capacity envelope under the CNDM. A 2 megawatt rooftop solar project at a site that matches the local demand pattern lands in the same phase as a 2 gigawatt offshore wind farm of comparable readiness; an unready 2 gigawatt project is moved to the legacy track and asked to come back when the readiness gap is closed. The trade is no longer a position date but a place in the network design. NESO does the design against the SSEP and CSNP, and the firm offer follows from the design rather than from the order of the queue.

DimensionBefore (legacy regime)After (TM04+ from April 2025)
Ordering principleFirst come, first served by application dateRanked against eight Gate 2 criteria and CNDM zonal envelope
Total contracted queue (transmission)~722 GW (Q4 2024)283 GW generation and storage progressed; 99 GW demand13
Indicative wait for an offer10 to 15 years from application; some 2037+ datesPhase 1 to 2030 or Phase 2 to 2035, set against project readiness
Position transferabilityPosition tradeable via project company saleGate 2 status held to the assessed project; reassessment on material change
Treatment of speculative positionsHeld in queue until withdrawn voluntarilyRetired through Gate 2 to Whole Queue process; capacity returned to the model
Network design basisDesigned against the contracted queueDesigned against the firm pipeline aligned to SSEP and CSNP
Charging boundaryShallowish at transmission; deep elements at some boundariesShallowish at transmission, with reform options under consultation for 2027 onwards
Flexibility off-rampAvailable case by case, mostly via Active Network ManagementBuilt into the assessment, with curtailment-priced flexibility offers as an explicit option
Milestone disciplineVariable; CMP361 introduced limited milestone tests in 2022Schedule 11 milestone tests at fixed intervals; two consecutive misses trigger cure-or-terminate

The before column is what a developer or a planner in 2023 had to work with. The after column is what they have to work with now, six weeks after the Gate 2 detailed results. The change is not cosmetic; it is the move from an administrative queue to a designed pipeline.

The eight Gate 2 criteria from section 18 of the CNDM

Section 18 of the CNDM is the heart of the reform for a developer reading the methodology for the first time. It names the eight criteria a project has to meet to qualify for Gate 2 status, the evidence the assessment looks for in each criterion, and how the criteria are weighted. The criteria are intentionally broad rather than narrow: they cover land rights, planning consent, technology readiness, financial commitment, system need, locational fit, deliverability, and an interoperability and data-quality test. A project that scores strongly across all eight lands in Phase 1 with a 2030 target; a project that scores strongly on system need and locational fit but is earlier in its land or consent journey lands in Phase 2 with a 2035 target; a project that scores weakly is asked to come back when the evidence is in place.

#CriterionWhat the assessment looks for
1Land rights to exclusivityOption, lease, or freehold over the site at the level of legal exclusivity that prevents a competing development. A heads of terms or letter of intent is below the threshold; an option agreement at exclusivity is at the threshold.
2Planning consent or a credible consent pathwayDevelopment consent order, planning permission, or a documented consent application in train with a credible decision date. For Nationally Significant Infrastructure Projects, the DCO route is the threshold; for distribution-scale projects, a section 73 or full planning application is the threshold.
3Technology readinessA specified, costed technology choice from a known supplier track. For generation, the equipment is at TRL 9 (commercial deployment) or has a documented path to TRL 9 by the energisation date. For storage, the battery chemistry and the inverter platform are named.
4Financial commitmentEvidence of equity or debt commitment proportionate to the project size. The threshold is documented capital allocation through a corporate decision, not a letter of intent. For large projects the threshold typically aligns with an investment committee paper or board minute.
5System need (alignment with SSEP and Clean Power 2030)The project is consistent with the technology mix and the regional capacity envelope set out in the SSEP pathway options of summer 2026 and the Clean Power 2030 advice. A project that proposes to add the same technology where the SSEP envelope is full is below threshold for system need.
6Locational fit (CNDM zonal map)The site sits within a zone where the CNDM envelope has remaining capacity, or the project comes with a credible plan to address the constraint (for example, a storage co-location that absorbs the voltage rise the underlying generator would cause).
7Deliverability against the Phase 1 (2030) or Phase 2 (2035) timelineThe project's milestone schedule (procurement, manufacture, civils, commissioning) is consistent with the energisation date being assessed. A project bidding for Phase 1 status with a procurement schedule that puts the long-lead transformer order three years after the Phase 1 cut-off is below threshold for deliverability.
8Data quality and interoperabilityThe application carries CIM-compliant data on the connection geometry, the protection settings, and the operational characteristics. This criterion is the one that ties the reform to the LTDS CIM workstream and to GC0139; the data quality on the application has to match the data quality the network is being designed against.2

The eight criteria are checked together. NESO assesses each criterion against the evidence the applicant supplies and produces a composite ranking. Phase 1 status is reserved for the projects that score strongly across all eight; Phase 2 status is for projects that score strongly on system need and locational fit and have a credible plan to close any other gap by a later milestone date. A project denied at Gate 2 is not denied a connection: it is asked to address the gap and to come back in the next application window in H2 2026 or a subsequent window.

The criteria interlock with the other workstreams in a way that matters for a developer planning evidence. Criterion 5 (system need) ties to the SSEP and to Clean Power 2030. Criterion 6 (locational fit) ties to the CNDM zonal map and to the LTDS Stage 2 model published 29 May 2026.1 Criterion 7 (deliverability) ties to the Capacity Market timetable for projects that need a CM contract to underwrite their finance; the T-4 2029/30 results of February 2026 are the relevant anchor for Phase 1 projects.8 Criterion 8 (data quality) ties to the LTDS data exchange under GC0139 and to the BSI CIM Engagement Hub. A team that prepares evidence for one criterion without thinking about the others tends to discover gaps late in the assessment; a team that maps the criteria onto its existing project documents at the start finds them straightforward to satisfy.

A queue walk from initial enquiry to energisation

The diagram above sketches the seven stages a project moves through. Each stage is set out in more depth below, noting what the developer needs to do, who owns the next step, and how the timescale compares with what the same stage looked like under the legacy regime.

Stage 1: initial enquiry and CUSC or DCUSA application

The first move is the developer's. For a transmission-connected project at 132 kilovolts and above (and in Scotland, for projects at 132 kilovolts), the application drops into the CUSC track and is addressed to NESO. For a distribution-connected project at 132 kilovolts or below in England and Wales, the application drops into the DCUSA track and is addressed to the host DNO. The application carries a data pack covering the proposed site, the connection voltage and capacity requested, the technology and the export profile, and the initial timeline. Under TM04+, the application is also expected to carry early evidence against the eight criteria; a developer who waits for the formal assessment to ask for the evidence loses the cycle.

Stage 2: TM04+ filter (months 0 to 2)

The TM04+ filter is the first NESO step. It checks the application against a baseline of data quality (criterion 8) and project readiness (a composite of criteria 1, 2, and 4). The filter is intentionally light: it weeds out applications that are not credible at the lodgement stage, freeing the more detailed assessment to focus on projects that are. Projects that drop out at the filter are not refused a connection; they are advised which criterion they fell short on and invited to lodge again when the gap is closed.

Stage 3: CNDM zonal placement (months 2 to 4)

The CNDM zonal placement is the geographic step. NESO maps the project onto the CNDM zonal capacity envelope to identify whether the proposed site sits in a zone with remaining headroom under the SSEP and CSNP, whether it co-ordinates with the other Gate 2 projects already in flight, and whether it needs to be matched to network reinforcement planned in the next CSNP cycle. The placement step is where a developer often discovers that a marginal-fit site can be made strong by a small adjustment: moving the substation by a kilometre into a zone with more headroom, or co-locating with storage to absorb the voltage rise.

Stage 4: the eight criteria assessment (months 4 to 6)

The G2CM assessment is the substantive step. NESO scores the project against each of the eight criteria using the evidence supplied. The output is a composite ranking and a Phase recommendation (Phase 1 for 2030 delivery, Phase 2 for 2035, or a referral back with named evidence gaps). The assessment is documented end to end; a developer receives the rationale for the Phase recommendation and the criterion-by-criterion scoring, which gives a clear basis for either accepting the offer or, if needed, lodging a revised application in a later window with the named gaps closed.

Stage 5: firm-offer issuance (months 6 to 8)

The firm offer issues within the current cycle's offer window, which for the April 2026 outcomes runs March 2026 to November 2026 in sequenced tranches by technology and connection voltage. The offer is a Bilateral Connection Agreement under CUSC for transmission or the equivalent under DCUSA for distribution. It names the connection point, the connection voltage, the Transmission Entry Capacity (or equivalent distribution capacity), the energisation date, the Schedule 11 milestone schedule, and the charging arrangements. The applicant has a two-month acceptance window from offer issue; an offer that is not accepted within the window lapses and the project returns to the next application window.

Stage 6: construction (2 to 4 years for most generation and storage)

Construction proceeds under Schedule 11 of the BCA. The applicant reports against milestone dates at fixed intervals (typically 6, 12, and 24 months from acceptance). The milestone tests are designed to catch a project that is slipping while there is still time to recover; missing two consecutive milestones triggers a cure-or-terminate notice with a 28-day cure period. A project that cures returns to the milestone schedule; a project that does not is terminated and its TEC is returned to the model, where it becomes available to other Phase 1 or Phase 2 projects in the next assessment window.

Stage 7: energisation (Phase 1 by 2030, Phase 2 by 2035)

Energisation is the final step. At transmission, the project completes its compliance under Grid Code CC.6 and Engineering Connection Conditions ECC.6, presents its compliance documents to NESO, and receives a Final Operational Notification.3 At distribution, the equivalent compliance is under Distribution Code DPC4 and the ENA Engineering Recommendations (G98 for micro-generation, G99 for everything above 16 amperes per phase).4 The project then enters operation under its TEC; the TEC is the formal capacity right it holds against the network model, and it is published in the Transmission Entry Capacity Register that NESO maintains and updates weekly.

Worked example: a 100 megawatt battery through the queue

To make the assessment concrete, this section walks a hypothetical 100 megawatt, two-hour battery energy storage project from initial enquiry to energisation. The site is in the East Midlands, near a 132 kilovolt substation with documented historic capacity to absorb storage exports during low-demand periods. The applicant is a developer with a portfolio of three other batteries operational in the Midlands. The example is not a real project; the figures are illustrative and the supplier names are anonymised, but the steps and the timescales match what a comparable project would face under the reformed regime in the H2 2026 application window.

Worked example: a hypothetical 100 megawatt battery against the eight Gate 2 criteria

Stage 1 (month 0): initial enquiry. The applicant submits a CUSC application to NESO for a 100 megawatt, two-hour battery at the named substation. The application names the connection voltage (132 kV), the export profile (full export on dispatch, charging during low-price periods), the initial commercial operation date (Q3 2029), and the technology (lithium-iron-phosphate cells with a named inverter platform at TRL 9).

Stage 2 (months 0 to 2): TM04+ filter. The application carries the baseline evidence: an option agreement at exclusivity over the site (criterion 1), a documented planning application in train with a credible decision date (criterion 2), a corporate decision allocating equity capital to the project (criterion 4), and CIM-compliant data on the connection geometry and protection settings (criterion 8). The filter passes.

Stage 3 (months 2 to 4): CNDM zonal placement. NESO places the project on the CNDM zonal map. The East Midlands zone has remaining capacity for storage but is approaching its envelope for generation; the project's role as a storage export-and-absorb asset is treated as additive to the system rather than competing with existing generation positions. The placement is favourable.

Stage 4 (months 4 to 6): the eight criteria. The assessment scores each criterion:

Criterion 1 (land rights): exclusivity option agreement, pass

Criterion 2 (planning): full application lodged with the local authority, credible Q4 2026 decision, pass

Criterion 3 (technology readiness): named inverter at TRL 9; named cell chemistry at TRL 9, pass

Criterion 4 (financial commitment): board-approved equity allocation, pass

Criterion 5 (system need): storage role consistent with SSEP and Clean Power 2030 storage envelope, pass

Criterion 6 (locational fit): East Midlands zone has remaining capacity for storage, pass

Criterion 7 (deliverability): procurement, civils and commissioning schedule consistent with Q3 2029 energisation, pass

Criterion 8 (data quality): application data CIM-compliant, validates against the NESO schema, pass

The project passes all eight criteria and is recommended for Phase 1 status (2030 delivery).

Stage 5 (months 6 to 8): firm offer. NESO issues a Bilateral Connection Agreement in the September 2026 tranche of the offer window. The BCA names a 132 kilovolt connection point at the host substation, a Transmission Entry Capacity of 100 megawatts, an energisation date of Q3 2029, the Schedule 11 milestone schedule, and the charging arrangement. The applicant accepts the offer within the two-month acceptance window.

Stage 6 (years 1 to 3 from acceptance): construction. The applicant procures the inverters and cells against the Schedule 11 milestone schedule, undertakes the civils at the site, and progresses the connection works at the host substation. Milestone reports are submitted at 6, 12, and 24 months from acceptance; each is passed without a cure-or-terminate trigger. In parallel, the applicant bids the project into the T-4 Capacity Market auction for delivery 2029/30, supported by a CfD-style risk-sharing arrangement on storage availability.8

Stage 7 (Q3 2029): energisation. The project completes commissioning, demonstrates compliance with Grid Code CC.6 and the Engineering Connection Conditions, and receives its Final Operational Notification. It enters operation under its 100 megawatt TEC, with the TEC published in the Transmission Entry Capacity Register and the project entered into the Embedded Capacity Register at the host DNO (storage is classified as generation for ECR purposes following CMP281 and DCP338).

Total elapsed time: approximately 40 months from initial enquiry to energisation. Under the legacy regime the same project would have lodged in 2023 with an indicative connection date in the late 2030s, contingent on the speculative pipeline ahead of it. The reformed regime brings the date forward by nearly a decade for a well-evidenced project, at the cost of an upfront evidence load the developer carries before the application is lodged.

The same walk applied to a less ready project would produce a different outcome. A project that scored strongly on system need and locational fit but had only a letter of intent on the land (criterion 1 below threshold) and a heads of terms on the cell supply contract (criterion 3 below threshold) would not pass Gate 2 at first lodgement; it would be advised to lodge again in the next window with the option agreement signed and the cell contract upgraded to a binding commercial term sheet. The point of the reformed regime is that the gap is named, the cycle to address it is short, and the position when the project does qualify is firm.

Primary sources

The most load-bearing sources are listed below.

  1. LTDS CIM Stage 2 and 3 Extension (Derogation) Letter, Ofgem, 13 May 2026. The network model the reformed queue is now being designed against. https://www.ofgem.gov.uk/sites/default/files/2026-05/LTDS-CIM-Stage-2-and-3-Extension-Derogation-Letter.pdf
  2. GC0139: Enhanced Planning-Data Exchange to Facilitate Whole System Planning, NESO, last updated 7 April 2026. The data-quality and interoperability workstream that criterion 8 of the eight Gate 2 criteria ties to. https://www.neso.energy/industry-information/codes/gc/modifications/gc0139-enhanced-planning-data-exchange-facilitate-whole-system-planning
  3. The Grid Code, NESO, Issue 6 Revision 37, 13 April 2026. Sets the technical compliance bar at stage 7 of the queue walk (Grid Code CC.6 and Engineering Connection Conditions ECC.6 for transmission-connected projects). https://www.neso.energy/industry-information/codes/grid-code-gc
  4. The GB Distribution Code, Issue 59, 24 April 2026, Distribution Code Review Panel. Sets the technical compliance bar for distribution-connected projects (DPC4 for operational voltage; DOC for system-wide co-ordination). https://www.dcode.org.uk/
  5. ENA G98 Issue 2, 10 March 2025. Connection requirements for fully type tested micro-generators up to 16 amperes per phase. https://dcode.org.uk/assets/250307ena-erec-g98-issue-2-(2025).pdf
  6. ENA G99 Issue 2, 10 March 2025. Connection requirements for generation above 16 amperes per phase, transposing Network Code RfG into the GB regime. https://dcode.org.uk/assets/250307ena-erec-g99-issue-2-(2025).pdf
  7. Connections Reform: Connections Network Design Methodology (CNDM) and Gate 2 Criteria Methodology (G2CM), NESO, CNDM dated 30 April 2025. The CNDM defines the zonal placement and names the eight Gate 2 criteria in section 18; the G2CM defines the procedural assessment against the criteria. Approved by Ofgem in the Connections Reform decision of April 2025. https://www.neso.energy/industry-information/connections-reform/connections-reform-design-documents-and-methodologies
  8. Capacity Market Final Auction Parameters letter (T-4 2029/30 and T-1 2026/27), DESNZ to NESO, February 2026. T-4 cleared 40.1 GW at £27.10 per kilowatt against a 39.4 GW target; the revenue anchor a Phase 1 connection project bids against. https://www.gov.uk/government/publications/capacity-market-auction-parameters-letter-from-desnz-to-neso-february-2026/final-auction-parameters-t-1-and-t-4-capacity-market-auctions
  9. Strategic Spatial Energy Plan (SSEP) methodology v.1, NESO with DESNZ, May 2025. Sets the spatial framework that criterion 5 (system need) and criterion 6 (locational fit) align to. Pathway options to Secretary of State summer 2026; final SSEP autumn 2027. https://www.neso.energy/what-we-do/strategic-planning/strategic-spatial-energy-planning-ssep
  10. SLC 25 of the Electricity Distribution Licence. The licence condition that produces the LTDS at intervals of not more than seven years; the network model the reformed queue is now being designed against. https://epr.ofgem.gov.uk/Content/Documents/Electricity Distribution Consolidated Standard Licence Conditions - Current Version.pdf
  11. Electricity Act 1989, s.6(1)(c) and section 16. The statutory parent of the licence regime; section 16 holds the duty to offer terms that the reform package operates within rather than replaces. https://www.legislation.gov.uk/ukpga/1989/29/section/6
  12. CSNP Methodology Approval Decision, Ofgem, April 2026. Approves the centralised strategic network plan against which the connections phasing is co-ordinated; T-CSNP due June 2026; final CSNP by end of 2028. https://www.ofgem.gov.uk/sites/default/files/2026-04/CSNP-Methodology-Approval-Decision.pdf
  13. NESO Connections Reform Gate 2 detailed results, April 2026. 283 GW generation and storage and 99 GW demand progressed; Phase 1 to 2030; Phase 2 to 2035; offer-issuance windows March to November 2026; next applications H2 2026. https://www.neso.energy/document/374936/download

Where a numerical claim sits behind a methodology table, the relevant section number is given inline (S18 CNDM section reference, G2CM criterion number). The Electricity Act 1989 holds the duty to offer terms in section 16 and the licence regime in section 6; Part 5 of the Energy Act 2023 transferred the queue-management duty from the former ESO to NESO when NESO was created on 1 October 2024.