Electrical substation with steel gantries, busbars and overhead conductors against a clear sky
A substation is where a wind farm, battery or factory takes its physical point on the wires. The connections process decides where that point is, who may use the capacity there, and when it will be ready. Photo: Pexels

How an Electricity Project Gets a Grid Connection

A wind farm, battery or large factory needs a physical point on the wires, permission to use capacity there, and a firm date when that capacity will be ready. The connections process decides those three things for thousands of projects in a queue that now tests readiness and strategic need, not just application date.

Scope: how a project joins the grid, the rules that decide its place, and the data behind those decisions. The wider market revenue, the physical network and the voltage limits are linked at the points they matter.

Sources and standards

Every reform date, queue volume and gate criterion resolves to a primary instrument: the Ofgem Connections Reform decision, the NESO Connections Network Design Methodology of 30 April 2025, the Gate 2 Criteria Methodology, the NESO Gate 2 detailed results of April 2026, the Ofgem connections end-to-end review, or an underlying statute (Electricity Act 1989, Energy Act 2023). Connection data sources include the per-DNO Embedded Capacity Registers, the NESO Data Sharing Infrastructure, and the ENA Open Networks tooling.

Where the connections queue stands after Gate 2

The Gate 2 detailed results that NESO published in December 2025 are the first end-to-end picture of the reformed queue.13 Across generation and storage, 283 gigawatts have been progressed to firm offers; across demand connections, 99 gigawatts. The portfolio is sorted into two phases. Phase 1 covers projects that NESO and Ofgem judge are needed and able to energise by 2030 to meet the Clean Power 2030 target. Phase 2 covers projects that are needed but on a 2035 horizon. Offer windows run from March 2026 to November 2026 in sequenced tranches by technology and connection voltage, and the next application window opens in the second half of 2026.

That is a different world from eighteen months earlier. The Ofgem Connections Reform decision of April 2025 retired the legacy first come, first served model, and NESO then published three methodologies in quick succession: the Connections Network Design Methodology, the Gate 2 Criteria Methodology, and the Gate 2 to Whole Queue process.7 A project that lodged an application in 2022 used to receive an indicative date set only by its position in the contracted-queue order, often a date in the late 2030s. A project lodging now is assessed against eight criteria and, if it qualifies, receives a firm Phase 1 or Phase 2 date. Projects that did not progress through the Gate 2 to Whole Queue assessment have moved to a withdrawal track, returning the capacity their offers had locked against the network model.

Two further moves shape the connection route. The Ofgem connections end-to-end review, with next steps published in December 2025, looks beyond the queue mechanics at the whole connection experience: faster processes, clearer connection data, and connection service standards that hold network operators to defined response times.14 Those service standards are expected to be carried into the next distribution price control: Ofgem's RIIO-ED3 methodology, the price control proposed for 2028 to 2033, is consulting on connection service standards and output incentives for the network operators, and the detail remains minded-to rather than settled while the consultation runs.16 The Long Term Development Statement Stage 2 publication of 29 May 2026, under Ofgem's derogation letter of 13 May 2026, sets out the distribution assets and the headroom the queue is being placed against.1

The reformed queue at a glance: from 722 GW to a 283 GW firm pipeline

Based on NESO's Connections Reform Gate 2 results (8 December 2025) and Ofgem's TMO4+ decision. Bars share one gigawatt scale; only the firm pipeline split (132 plus 151) is a conserved total.

How NESO's TMO4+ Gate 2 reform sorted Great Britain's electricity connections queue: a contracted queue about four times the size of what Britain needs by 2030, narrowed to a firm dated pipeline of 283 gigawatts A proportional comparison on one gigawatt scale, with a dashed reference line marking the roughly 200 to 225 gigawatts of generation Britain needs by 2030. The contracted queue in late 2024 was 722 gigawatts, about four times that need, drawn as the longest bar, far longer than the firm pipeline below it. Gate 2 firm offers for generation and storage total 283 gigawatts, split into Phase 1 of 132 gigawatts for delivery to 2030 and Phase 2 of 151 gigawatts for 2035, a bar only a little longer than the need line. Separately, 216 gigawatts were placed in Gate 1, deferred and able to reapply at later windows; and NESO has said more than 300 gigawatts of the old queue will not move forward. Counted apart from the generation queue, almost 100 gigawatts of transmission demand connections also progressed. The figures are NESO's published outcomes from 8 December 2025; the deferred and not-moving-forward buckets do not sum to the queue total because they come from different source extracts and demand is counted separately. From a 722 GW queue to a 283 GW firm pipeline: the Gate 2 reform NESO's TMO4+ reform sorted a contracted queue about four times the size of what Britain needs by 2030 into a firm, dated pipeline. Published outcomes, 8 December 2025. needed by 2030: about 200-225 GW of generation Contracted queue, late 2024 722 GW Firm offers: generation and storage 283 GW Phase 1, to 2030: 132 GW Phase 2, to 2035: 151 GW Gate 1: deferred, may reapply later 216 GW Will not move forward (NESO) more than 300 GW Counted separately, not part of the generation queue above: Transmission demand connections almost 100 GW Bars share one scale. Deferred and not-moving-forward are NESO's published outcomes; they do not sum to the queue total (different source extracts, and demand is counted apart).

In late 2024 the contracted transmission queue held about 722 gigawatts, roughly four times the 200 to 225 gigawatts of generation Britain needs by 2030. The Gate 2 reform sorted it: 283 gigawatts of generation and storage received firm dated offers, 132 gigawatts in Phase 1 to 2030 and 151 gigawatts in Phase 2 to 2035, a pipeline close to the assessed need. A further 216 gigawatts were placed in Gate 1, deferred but able to reapply, and NESO has said more than 300 gigawatts of the old queue will not move forward. Almost 100 gigawatts of transmission demand connections progressed as well, counted separately from generation. The deferred and not-moving-forward figures are NESO's published outcomes and do not sum to the queue total, because they come from different source extracts and demand is counted apart.

The journey from first enquiry to energisation

A project moves through seven stages from its first enquiry to the day it is switched on. The first stage belongs to the developer; the middle stages belong to NESO, which screens, places and scores the project; the later stages are the firm offer, the build, and the final switch-on. Each stage names who owns the next step and the rough time it takes. The two off-ramps matter as much as the main path: a legacy project that no longer fits the plan leaves through the orderly withdrawal route, and a project that cannot get firm capacity yet can take a flexible connection that accepts curtailment in exchange for an earlier date.

New steel transmission towers being erected in an open field, with construction plant and barriers at their base
New transmission towers under construction in open country. Energisation is the last of seven stages a project moves through, after the readiness screen, the network placement and the firm offer. Photo: Pexels
  1. 1
    Initial enquiry and application

    The developer applies to NESO for a transmission connection at 132 kilovolts and above, or to the host distribution network operator for a smaller connection. The application names the site, the voltage and capacity wanted, the technology and the export profile, with early evidence against the eight criteria.

    Month 0 · the applicant
  2. 2
    TM04+ readiness and data screen

    NESO checks the application against a baseline of data quality and project readiness. The screen is deliberately light: it sets aside applications that are not credible yet so the detailed assessment can focus on those that are. A project set aside is told which test it fell short on and invited back.

    Month 0 to 2 · NESO
  3. 3
    Placement on the network design map

    NESO places the project on the Connections Network Design Methodology zonal map, against the Strategic Spatial Energy Plan and the Centralised Strategic Network Plan. This is where a marginal site is often made strong by a small change: shifting the connection point, or co-locating storage to absorb the voltage rise.

    Month 2 to 4 · NESO
  4. 4
    Assessment against the eight Gate 2 criteria

    NESO scores the project against the eight criteria in the Gate 2 Criteria Methodology and produces a composite ranking with a phase recommendation: Phase 1 for 2030 delivery, Phase 2 for 2035, or a referral back with named evidence gaps. The scoring is documented criterion by criterion.

    Month 4 to 6 · NESO
  5. 5
    Firm connection offer

    The firm offer is a Bilateral Connection Agreement naming the connection point, the voltage, the entry capacity, the energisation date, the milestone schedule and the charges. The applicant has two months to accept; an offer not accepted in the window lapses and the project returns to a later application window.

    Month 6 to 8 · NESO and the applicant
  6. 6
    Construction against milestones

    The project builds under the agreement's milestone schedule, reporting at fixed intervals (typically 6, 12 and 24 months). The milestone tests catch a slipping project while there is still time to recover; missing two in a row triggers a cure-or-terminate notice with a short cure period.

    2 to 4 years for most generation and storage · the applicant
  7. 7
    Energisation and switch-on

    The project proves it meets the technical rules, under the Grid Code for transmission or the Distribution Code and the ENA connection recommendations for distribution, and receives its Final Operational Notification.34 It then operates under its capacity right, recorded in the public register that NESO updates each week.

    Phase 1 by 2030, Phase 2 by 2035 · the applicant and NESO

The two off-ramps sit beside this path. A legacy project that no longer fits the strategic plan leaves through the Gate 2 to Whole Queue withdrawal route, which returns its locked capacity to the model for projects that can use it. A project that cannot be given firm capacity at its chosen point, because the local network has no headroom yet, can instead take a flexible connection under Active Network Management: it connects sooner but accepts curtailment during the hours when the network is full, in exchange for a lower charge or an earlier date.

The reform chain from April 2025 to April 2026

The reform is a chain of instruments, not a single document. It starts with the Ofgem Connections Reform decision of April 2025, which approved the policy direction and authorised NESO to publish the methodologies that put it into effect.7 The decision sits under the Electricity Act 1989 licence regime and the queue-management duty that NESO inherited under Part 5 of the Energy Act 2023.11 It did not change the duty to offer connection terms in section 16 of the Electricity Act; it changed the rules NESO follows when it frames the offer.

The Connections Network Design Methodology (30 April 2025)

The methodology is the spatial and engineering document of the reform. It sets out how NESO designs the network against a firm pipeline rather than against the whole contracted queue, using zonal capacity envelopes aligned to the Strategic Spatial Energy Plan and to the Centralised Strategic Network Plan, the methodology for which Ofgem approved in April 2026.12 A project lodging after 30 April 2025 is placed against the zonal map and its capacity envelope, not against the older application-date order. Section 18 of the methodology names the eight criteria a project must meet to qualify for Gate 2, which the Gate 2 Criteria Methodology then sets out in full.

The Gate 2 Criteria Methodology

The Gate 2 Criteria Methodology is the procedural document. It defines how NESO assesses an application against the eight criteria, the evidence required for each, and the scoring and pass thresholds. It also sets the cadence of application windows and the offer windows that follow; the first offer window under the reform opened in March 2026 and runs to November 2026, sequenced by technology and voltage. A developer preparing a new application reads this document first, because it states what evidence the team must assemble and on what schedule.

The Gate 2 to Whole Queue process

The Gate 2 to Whole Queue process handles the legacy backlog. By the fourth quarter of 2024 the contracted transmission queue had reached roughly 722 gigawatts. The process applies the same eight criteria to projects lodged before April 2025, sorting which qualify for Phase 1 or Phase 2 and which are retired through an orderly withdrawal of the offer. Retiring those offers returns their locked entry capacity, which is the mechanism that brought the queue down from about 722 gigawatts to the structured 283 gigawatts of generation and storage plus 99 gigawatts of demand.13 The duty that holds NESO and the network operators to publishing the network model the reform runs against is Standard Licence Condition 25, which requires the Long Term Development Statement at intervals of no more than seven years; the Stage 2 publication of 29 May 2026 is the most recent step in that cycle.10

DateInstrumentWhat it does
April 2025Ofgem Connections Reform decisionApproves the reform package and authorises NESO to publish the methodologies that follow.
30 April 2025Connections Network Design MethodologyPlaces new connections against the SSEP and CSNP envelopes; section 18 names the eight Gate 2 criteria.
May 2025Strategic Spatial Energy Plan methodologySets the strategic spatial framework the network design aligns to; pathway options to the Secretary of State in summer 2026.9
2025Gate 2 Criteria MethodologyDefines the procedural assessment against the eight criteria, the evidence required, and the pass thresholds.
December 2025Ofgem connections end-to-end review, next stepsLooks beyond the queue at the whole connection experience: faster processes, clearer data, connection service standards.14
April 2026Gate 2 detailed results (NESO)283 GW generation and storage and 99 GW demand progressed; Phase 1 to 2030; Phase 2 to 2035.13
April 2026CSNP methodology approval (Ofgem)Approves the network plan methodology that the connections phasing is co-ordinated against.12
29 May 2026LTDS Stage 2 publicationThe network model a developer can plan a new application against in the second-half-2026 window.1

The queue before and after TM04+

Setting the old and new side by side makes the reform easy to read. The headline numbers are stark, but the more important change is in the mechanics. Before the TM04+ reform, the queue ordered applicants by the date their compliant application arrived. A 2 megawatt rooftop solar project sat ahead of a 2 gigawatt offshore wind farm with full development consent if the rooftop application landed first. The position carried a firm date and could be traded by selling the project company, and the date it implied was often more than a decade away even for small, ready, well-sited projects, because it depended on the speculative pipeline ahead of it that had no obligation to build.

After TM04+, the position depends on the readiness of the project against the eight criteria and its fit with the zonal capacity envelope. A ready 2 megawatt project that matches the local demand pattern lands in the same phase as a 2 gigawatt offshore wind farm of comparable readiness; an unready large project is moved to the legacy track and asked to return when the readiness gap is closed. What a developer trades is no longer a position date but a place in the network design, and the firm offer follows from the design rather than from the order of arrival.

DimensionBefore (legacy regime)After (from April 2025)
Ordering principleFirst come, first served by application dateRanked against eight Gate 2 criteria and the zonal envelope
Contracted queue (transmission)About 722 GW by late 2024283 GW generation and storage; 99 GW demand progressed13
Indicative wait for an offer10 to 15 years; some dates beyond 2037Phase 1 to 2030 or Phase 2 to 2035, set by readiness
Position transferTradeable by selling the project companyGate 2 status held to the assessed project; reassessed on material change
Speculative positionsHeld until withdrawn voluntarilyRetired through the Gate 2 to Whole Queue process; capacity returned
Network design basisAgainst the whole contracted queueAgainst the firm pipeline aligned to SSEP and CSNP
Flexible connectionCase by case, mostly via Active Network ManagementBuilt into the assessment as a priced option with curtailment terms
Milestone disciplineVariable; limited milestone tests from 2022Milestone tests at fixed intervals; two consecutive misses trigger cure-or-terminate

The eight Gate 2 criteria from section 18 of the CNDM

Section 18 of the Connections Network Design Methodology is the heart of the reform for a developer reading it for the first time. It names the eight criteria a project must meet to qualify for Gate 2, the evidence each looks for, and how they are weighted. The criteria are broad rather than narrow: they cover land rights, planning, technology, finance, system need, locational fit, deliverability, and a data-quality test. A project that scores strongly across all eight lands in Phase 1 with a 2030 target; a project strong on system need and locational fit but earlier in its land or consent journey lands in Phase 2 with a 2035 target; a project that scores weakly is asked to return when the evidence is in place.

#CriterionWhat the assessment looks for
1Land rights to exclusivityAn option, lease or freehold over the site at the level of legal exclusivity that blocks a competing development. A heads of terms is below the threshold; an option at exclusivity is at it.
2Planning consent or a credible pathwayA development consent order, planning permission, or a documented application in train with a credible decision date.
3Technology readinessA specified, costed technology from a known supplier track, at commercial-deployment readiness or with a documented path to it by the energisation date.
4Financial commitmentEvidence of equity or debt proportionate to the project, through a corporate decision such as a board minute, not a letter of intent.
5System needThe project fits the technology mix and the regional capacity envelope in the SSEP pathways and the Clean Power 2030 advice. Adding the same technology where the envelope is full is below threshold.
6Locational fitThe site sits in a zone with remaining capacity, or comes with a credible plan to address the constraint, such as co-locating storage to absorb the voltage rise the generator would cause.
7Deliverability against the phase timelineThe procurement, manufacture, civils and commissioning schedule is consistent with the 2030 or 2035 energisation date being assessed.
8Data quality and interoperabilityThe application carries model-compliant data on the connection geometry, protection settings and operating characteristics. This is the test that ties the application to the LTDS data workstream and to GC0139.2

The eight are checked together as a composite ranking. The criteria also interlock: system need ties to the SSEP and Clean Power 2030, locational fit ties to the zonal map and the LTDS Stage 2 model, deliverability ties to the long-lead procurement schedule, and data quality ties to the same model-based exchange the network is being designed against. A team that maps the criteria onto its existing project documents at the start tends to find them straightforward; a team that prepares one criterion at a time tends to discover gaps late in the assessment.

Connections data: what is open, what is protected, and how the Data Sharing Infrastructure sits between them

Based on the Ofgem connections end-to-end review, the per-DNO Embedded Capacity Registers published under Data Best Practice, the NESO Data Sharing Infrastructure, and the ENA Open Networks tooling. The figure sorts connection data into three kinds, open, protected and governed-sharing, and shows the decision users each kind serves.1415

Connection data sorted into open data, protected sensitive data, and data shared under governance, with the decision users each kind serves Three lane cards across the top. The first lane, open data, is published for anyone and holds the Embedded Capacity Register, queue position and phase, and headroom and network maps. The second lane, sensitive data, is access-controlled and holds detailed protection settings, customer and site details, and security and resilience data. The third lane, data shared via the Data Sharing Infrastructure, is governed discovery and sharing and holds cross-operator planning data found through a catalogue and shared under set permissions. Below the three lanes a band names the decision users: developers choosing where to apply, NESO designing the network, network operators running the local system and publishing the register, and Ofgem holding the connection service standards. An arrow runs from each lane down to the decision-users band, labelled anyone can read it, only the entitled can read it, and shared under governance. Connection data falls into three kinds, each serving the same decision users Open data Published for anyone to use Embedded Capacity Register Queue position and phase Headroom and network maps Generation availability data Sensitive data Access-controlled, not public Detailed protection settings Customer and site details Security and resilience data Commercially sensitive terms Shared via the DSI Governed discovery and sharing Cross-operator planning data Found through a catalogue Shared under set permissions Audited, time-bound access anyone can read it only the entitled shared under governance Decision users Developers choose where to apply, using the open queue, register and headroom data. NESO designs the network and runs the Gate 2 assessment across all three kinds of data. Network operators run the local system and publish the Embedded Capacity Register. Ofgem holds the connection service standards and reviews how open the data is.

The reform depends on data as much as on rules. Open data lets a developer identify a sensible connection point before applying; protected data keeps customer, security and commercial details safe; and the Data Sharing Infrastructure is the governed middle path that lets operators share planning data with each other without making it fully public. The Ofgem end-to-end review pushes for more of the queue and headroom picture to move into the open column over time.

Connections data: what is open, what is protected, and who decides

A reformed queue only works if everyone can see the same picture of where capacity is and where it is full. Connection decisions now rest on data, and that data falls into the three kinds the diagram above sets out. The first kind is open. Each distribution network operator publishes an Embedded Capacity Register, a public list of the generation and storage connected and contracted on its network, and headroom and constraint maps that show where capacity remains. NESO publishes the queue position and phase from the Gate 2 results, so a developer can see what has already been progressed in a given area.13 Open data is what lets a developer choose a sensible point to apply before spending money on an application.

The second kind is protected. Detailed protection settings, customer and site details, security and resilience information, and commercially sensitive contract terms are not published, because releasing them would harm a customer, a competitor position, or the security of the network. The judgement about what to open and what to protect follows Data Best Practice and a triage process that weighs five legitimate reasons to restrict access: privacy, security, negative consumer impact, commercial sensitivity, and law or regulation. The default is open; the burden is on the holder to justify keeping something closed.

The third kind sits between the two. The Data Sharing Infrastructure is a governed way for energy organisations to discover and share data that should not be fully public but does need to move between operators, for example the cross-operator planning data that whole-system network design depends on.15 A holder lists a dataset in a shared catalogue; a user finds it and requests access; the access is granted under set permissions, time-bound and audited. The infrastructure is being delivered by NESO and is governed under Ofgem's decision on the governance of data sharing infrastructure, which sets who can decide what is shared and on what terms.

The tooling that ties this together is co-ordinated through the ENA Open Networks programme, which keeps the registers and the connection-data formats consistent across the fourteen network operators and runs shared tools such as Connect Direct, which helps a developer find which operator and which part of the network to approach.17 The Ofgem connections end-to-end review is the policy push behind all of this: among its next steps is a commitment to make more of the queue, the headroom and the connection-status picture open and timely, so that the data a developer relies on to choose a connection point is as current as the model NESO designs against.14 Holding the network operators to that, through connection service standards now and through the proposed RIIO-ED3 incentives later, is how the data side of the reform is meant to be enforced.16

Worked example: a 100 megawatt battery through the queue

To make the assessment concrete, the example below walks a hypothetical 100 megawatt, two-hour battery from first enquiry to energisation. The site is in the East Midlands, near a 132 kilovolt substation with documented historic capacity to absorb storage exports during low-demand periods. The developer has three other batteries already operational in the Midlands. The figures are illustrative and the suppliers anonymised, but the steps and timescales match what a comparable project would face in the second-half-2026 application window.

High-voltage substation equipment with insulators, bushings and busbars connecting plant to the network
High-voltage equipment at a substation, where a battery or generator connects to the network. The worked example below takes a 100 megawatt battery to a 132 kilovolt connection point like this one. Photo: Pexels

A hypothetical 100 megawatt battery against the eight Gate 2 criteria

Stage 1 (month 0): enquiry. The developer applies to NESO for a 100 megawatt, two-hour battery at the named substation, naming the connection voltage (132 kV), the export profile (full export on dispatch, charging during low-price periods), the target commercial operation date (third quarter 2029), and the technology (lithium-iron-phosphate cells with a named inverter platform at commercial readiness).

Stage 2 (months 0 to 2): readiness screen. The application carries the baseline evidence: an option agreement at exclusivity over the site (criterion 1), a planning application in train with a credible decision date (criterion 2), a corporate decision allocating equity (criterion 4), and model-compliant connection data (criterion 8). The screen passes.

Stage 3 (months 2 to 4): placement. NESO places the project on the zonal map. The East Midlands zone has remaining capacity for storage but is near its envelope for generation; the battery's role as an export-and-absorb asset is treated as additive to the system rather than competing with existing generation. The placement is favourable.

Stage 4 (months 4 to 6): the eight criteria. The assessment scores each criterion:

1 land rights: exclusivity option agreement, pass

2 planning: full application lodged, credible decision in late 2026, pass

3 technology: named inverter and cell chemistry at commercial readiness, pass

4 finance: board-approved equity allocation, pass

5 system need: storage role consistent with the SSEP storage envelope, pass

6 locational fit: East Midlands zone has remaining storage capacity, pass

7 deliverability: build schedule consistent with third quarter 2029, pass

8 data quality: application data model-compliant, validates on submission, pass

The project passes all eight and is recommended for Phase 1 status, with a 2030 delivery horizon.

Stage 5 (months 6 to 8): firm offer. NESO issues a Bilateral Connection Agreement in the September 2026 tranche, naming a 132 kilovolt connection point, a 100 megawatt entry capacity, an energisation date in the third quarter of 2029, the milestone schedule and the charges. The developer accepts within the two-month window.

Stage 6 (years 1 to 3): construction. The developer procures the inverters and cells against the milestone schedule, undertakes the civil works, and progresses the connection works at the substation. Milestone reports at 6, 12 and 24 months each pass without a cure-or-terminate trigger. In parallel the project bids into the T-4 Capacity Market auction for 2029/30 delivery.8

Stage 7 (third quarter 2029): energisation. The project completes commissioning, proves compliance under the Grid Code, and receives its Final Operational Notification. It enters operation under its 100 megawatt capacity right, which is recorded in the public capacity register and in the host operator's Embedded Capacity Register.

Elapsed time: about 40 months from enquiry to energisation

Under the legacy regime the same project would have lodged in 2023 with an indicative date in the late 2030s, contingent on the speculative pipeline ahead of it. The reform brings the date forward by nearly a decade for a well-evidenced project, at the cost of an upfront evidence load the developer carries before the application is lodged. A less ready project, with only a letter of intent on the land and a heads of terms on the cells, would not pass at first lodgement; it would be told exactly which gaps to close and invited back in the next window.

Primary sources

The most load-bearing sources for how a project gets a connection are listed below.

  1. LTDS CIM Stage 2 and 3 Extension (Derogation) Letter, Ofgem, 13 May 2026. The network model the reformed queue is designed against. https://www.ofgem.gov.uk/sites/default/files/2026-05/LTDS-CIM-Stage-2-and-3-Extension-Derogation-Letter.pdf
  2. GC0139: Enhanced Planning-Data Exchange to Facilitate Whole System Planning, NESO, last updated 7 April 2026. The data-quality and interoperability workstream that criterion 8 ties to. https://www.neso.energy/industry-information/codes/gc/modifications/gc0139-enhanced-planning-data-exchange-facilitate-whole-system-planning
  3. The Grid Code, NESO, Issue 6 Revision 37, 13 April 2026. The technical compliance bar at energisation for transmission-connected projects. https://www.neso.energy/industry-information/codes/grid-code-gc
  4. The GB Distribution Code, Issue 59, 24 April 2026, Distribution Code Review Panel. The technical compliance bar for distribution-connected projects. https://www.dcode.org.uk/
  5. ENA G98 Issue 2, 10 March 2025. Connection requirements for fully type tested micro-generators up to 16 amperes per phase. https://dcode.org.uk/assets/250307ena-erec-g98-issue-2-(2025).pdf
  6. ENA G99 Issue 2, 10 March 2025. Connection requirements for generation above 16 amperes per phase. https://dcode.org.uk/assets/250307ena-erec-g99-issue-2-(2025).pdf
  7. Connections Reform: Connections Network Design Methodology and Gate 2 Criteria Methodology, NESO, CNDM dated 30 April 2025. Defines the zonal placement and names the eight Gate 2 criteria in section 18; approved by Ofgem in the Connections Reform decision of April 2025. https://www.neso.energy/industry-information/connections-reform/connections-reform-design-documents-and-methodologies
  8. Capacity Market final auction parameters (T-4 2029/30 and T-1 2026/27), DESNZ to NESO, February 2026. T-4 cleared 40.1 GW at 27.10 pounds per kilowatt against a 39.4 GW target. https://www.gov.uk/government/publications/capacity-market-auction-parameters-letter-from-desnz-to-neso-february-2026/final-auction-parameters-t-1-and-t-4-capacity-market-auctions
  9. Strategic Spatial Energy Plan methodology, NESO with DESNZ, May 2025. The spatial framework that criteria 5 and 6 align to; pathway options to the Secretary of State in summer 2026. https://www.neso.energy/what-we-do/strategic-planning/strategic-spatial-energy-planning-ssep
  10. SLC 25 of the Electricity Distribution Licence. The licence condition that produces the Long Term Development Statement at intervals of no more than seven years. https://epr.ofgem.gov.uk/Content/Documents/Electricity Distribution Consolidated Standard Licence Conditions - Current Version.pdf
  11. Electricity Act 1989, section 6 and section 16. The statutory parent of the licence regime; section 16 holds the duty to offer connection terms that the reform operates within rather than replaces. https://www.legislation.gov.uk/ukpga/1989/29/section/6
  12. CSNP methodology approval decision, Ofgem, April 2026. Approves the centralised strategic network plan methodology that the connections phasing is co-ordinated against. https://www.ofgem.gov.uk/decision/approval-nesos-csnp-methodology
  13. NESO Connections Reform Gate 2 detailed results, April 2026. 283 GW generation and storage and 99 GW demand progressed; Phase 1 to 2030; Phase 2 to 2035; offer windows March to November 2026. https://www.neso.energy/industry-information/connections-reform/connections-reform-results
  14. Connections End-to-end Review: updated proposals and next steps, Ofgem, December 2025. Faster connection processes, more open connection data, and connection service standards for network operators. https://www.ofgem.gov.uk/consultation/connections-end-end-review-updated-proposals-and-next-steps
  15. Data Sharing Infrastructure, NESO, with Ofgem's governance of data sharing infrastructure decision. The governed means to discover and share energy data that is not fully open. https://www.neso.energy/about/our-projects/virtual-energy-system/data-sharing-infrastructure-dsi
  16. RIIO-ED3 sector specific methodology consultation, Ofgem. The electricity distribution price control proposed for 2028 to 2033; consulting on connection service standards and output incentives. Proposals are minded-to while the consultation runs. https://www.ofgem.gov.uk/consultation/sector-specific-methodology-consultation-electricity-distribution-price-control-ed3
  17. ENA Open Networks programme. Co-ordinates connection data and tooling across the network operators, including Connect Direct and the Embedded Capacity Registers. https://www.energynetworks.org/industry-info/open-networks

The duty to offer connection terms sits in section 16 of the Electricity Act 1989; Part 5 of the Energy Act 2023 transferred the queue-management duty to NESO when it was created on 1 October 2024.