The Great Britain energy data lifecycle from a meter reading to a settled consumer bill in May 2026, with the BSC P408 settlement run and a worked example for a 1,200 kWh per month household

The lifecycle of a single half-hourly meter observation runs in one continuous chain, from the moment it is recorded on a smart meter at the close of a half-hour through to the moment the corresponding pound or pence settles on a consumer bank statement. The lifecycle has seven stages: measurement at the meter; validation of the reading; aggregation by the supplier and the central settlement system; settlement under the Balancing and Settlement Code; reconciliation across the SF, R1, R2, R3 and RF windows; billing to the consumer; and payment by the consumer to the supplier. Each stage is a separate technical, contractual and regulatory event, and each carries a specific institution, format and cadence. The BSC P408 modification is the rule that holds the settlement step together under Market-wide Half Hourly Settlement; the MHHS migration that began on 22 October 2025 and cuts over in July 2027 is the largest single change to that step since the New Electricity Trading Arrangements went live in 2001. A worked end-to-end example closes the account, walking a representative domestic household consuming 1,200 kilowatt-hours per month on a Time of Use tariff through each of the seven stages with real Q2 2026 prices, and checking the final bill against the Q2 2026 Default Tariff Cap.

Last verified 28 May 2026

Sources and standards

Every regulatory milestone, settlement cadence and quantitative claim in the lifecycle resolves to a primary publication from Elexon (the Balancing and Settlement Code and the MHHS programme), Ofgem (the Default Tariff Cap and the LTDS Direction), NESO (BMRS Insights Solution and the Connections Reform Gate 2 results), DESNZ (the Energy Smart Data and Privacy Framework and the Capacity Market auction parameters), or an instrument on legislation.gov.uk. Section blocks carry the source identifier list as a data-source-id

Where the data lifecycle stands in May 2026

The account that follows stays short on news and long on mechanics, but five changes in the last twelve months are worth setting down before the stages are walked in turn. The first is the Market-wide Half Hourly Settlement migration. BSC modification P408 carries the consequential changes to the Balancing and Settlement Code and to its subsidiary documents for the move to half-hourly settlement for every electricity meter point.6 Operational migration began on 22 October 2025 under Milestone M11; by mid-quarter Q1 2026 ten million Meter Point Administration Number initiations were complete across Milestones M10 to M13; the cutover at Milestone M16 lands in July 2027, after which every electricity settlement in Great Britain is half-hourly for every consumer, not only for the Time of Use minority.4

The second change is the Insights Solution. The Balancing Mechanism Reporting Service was retired on 31 May 2024 after twenty years of service; the Insights Solution at bmrs.elexon.co.uk took its place, with the IRIS streaming endpoint as the live publish-subscribe feed for the same canonical datasets (system price, accepted balancing volumes, demand and generation outturn) plus the new MHHS-related reporting fields that the legacy platform could not have hosted.2 Every page citation in this workspace that resolves to a half-hour balancing number traces back to the Insights Solution as the primary source.

The third change is the Default Tariff Cap. The Q2 2026 cap effective from 1 April 2026 fell six point six percent against the Q1 2026 cap, to one thousand six hundred and forty one pounds per year for a typical dual-fuel direct debit household, after wholesale gas prices fell through Q1 2026 as European storage refilled faster than forecast and weather was milder than the ten-year average.8 The cap is the quarterly ceiling Ofgem sets on the standard variable tariff that any household not on a fixed-term deal pays; the five-component decomposition (wholesale, network, policy, operating, margin) is the headline number a policy reader needs at this stage, because each component is the output of a different lifecycle stage and a different market segment.

The fourth change is the NESO Data Portal cadence. The portal publishes operational forecasts, the generation mix, transmission outage data, demand forecasts and capacity-market timetables in machine-readable form under the NESO Open Licence, with the documented publication schedule that any consumer of operational data can plan a job pipeline against.3 The Carbon Intensity API, run jointly with the University of Oxford, publishes carbon-intensity forecasts at thirty-minute granularity by GB region; from May 2026 onward this is the canonical primary feed for any analyst computing a carbon-weighted view of the half-hourly market.

The fifth change is the Energy Smart Data and Privacy Framework. DESNZ published the framework in March 2026 as the policy framework for the energy-smart-data scheme that the Data (Use and Access) Act 2025 enables; the framework sets the rules for how a consumer authorises a third party (a price-comparison service, a tariff-switching service, an advice service) to read the consumer's half-hourly data and act on it on the consumer's behalf.7 The framework is the consumer-side counterpart to MHHS: MHHS makes the half-hourly data exist for every meter; the framework defines how a consumer can authorise the use of that data for a service that sits outside the supplier relationship.

The lifecycle that the seven stages below describe sits on top of those five changes. Five of the seven stages are mechanically the same as they were in 2024 (measurement at the meter, validation at the supplier, aggregation at the Grid Supply Point Group, billing to the consumer, payment by the consumer); two of the seven stages (settlement under BSC P408, and the reconciliation timetable that follows it) are in active migration and look materially different in May 2026 than they did in May 2024.

The seven stages of the energy data lifecycle, with worked numbers for a representative 1,200 kWh per month household on a Time of Use tariff

Based on Elexon BSC Section S, the BSC P408 modification report, the Q2 2026 Default Tariff Cap determination from Ofgem and the NESO Insights Solution cadence. The seven-stage lifecycle is the canonical lead diagram. The numbers under each stage are the worked output for the representative 1,200 kilowatt-hour per month household on a Time of Use tariff walked through end to end at the foot of the account.

The seven-stage Great Britain energy data lifecycle from measurement at a SMETS2 meter through validation, aggregation, settlement, reconciliation, billing and payment, with worked numbers for a representative 1,200 kWh per month household on a Time of Use tariff in Q2 2026 A horizontal sequence of seven coloured stages reading left to right. Stage 1 is measurement at the meter (teal). Stage 2 is validation at the supplier (amber). Stage 3 is aggregation to the Grid Supply Point Group (blue). Stage 4 is settlement under BSC P408 (orange). Stage 5 is reconciliation across the SF, R1, R2, R3 and RF windows (purple). Stage 6 is the consumer bill (green). Stage 7 is payment by direct debit (slate). Each stage has a header bar with the stage number, a title, three lines of mechanism description, and a worked-number footer showing what the representative 1,200 kWh per month household contributes at that stage. A bottom band names the institution responsible for each stage (DCC, supplier, Elexon and the central settlement system, the supplier billing engine, the consumer bank). Seven stages, one continuous lifecycle. Read left to right. Stage 1 Measurement at the meter SMETS2 records active import at the close of each half-hour and signs the observation. DCC carries it over the SMETS2 comms hub. Worked number 48 obs / day 40 kWh / day peak share 0.42 Stage 2 Validation at the supplier Supplier ingests the read, runs validation and substitution rules on missing data. Estimated reads resolve to actuals by R1 to R3. Worked number 99.7 percent validated at SF remainder by R1 Stage 3 Aggregation to GSP Group Supplier aggregates to GSP Group and applies the line loss factor class. Submits to central settlement system in canonical MHHS data format. Worked number 1.55 kWh / 1.47 LLFC uplift 5 percent LV class 01 Stage 4 Settlement under P408 Central settlement computes imbalance volume and cash position per party per half-hour. SBP and SSP land on the Insights Solution and IRIS. Worked number SF at D+14 WD cash-out PAR1 first cash position Stage 5 Reconciliation SF, R1, R2, R3, RF Five runs across fourteen months. Each run pulls in more validated reads and corrects the cash position. RF freezes the books at D+14 mo. Worked number R1 +0.04 percent R2 +0.01 percent RF locked Apr 2027 Stage 6 Billing to the consumer Supplier issues the bill, monthly or quarterly. Energy, standing charge, VAT and policy pass-through resolve on the bill. Cap-constrained. Worked number £136.75 / month £1,641 / year Q2 2026 cap typical Stage 7 Payment by direct debit Consumer pays by direct debit, standing order or prepayment top-up. Supplier credit cover at Elexon backs the cash leg to settlement. Worked number £136.75 / month direct debit SoLR backstop DCC + SMETS2 meter Smart Energy Code Supplier billing engine BSC Section S GSP Group + LLFC BSC P0244 / D-flow Elexon central settlement BSC P408 under MHHS BSC Section S timetable SF, R1, R2, R3, RF Supplier bill engine Default Tariff Cap Consumer bank BACS direct debit Worked end-to-end: 1,200 kWh per month household on a Time of Use tariff, 12.0 percent peak share, Q2 2026 Default Tariff Cap of £1,641 per year as the cap reference.

The seven stages run left to right and each contains a worked number from the representative household. The institutions band names the actor responsible for each stage; the bottom legend states the worked end-to-end input. The full step-by-step calculation appears in the worked-example section at the foot of the page.

The statutory frame: the Balancing and Settlement Code and BSC modification P408

The Balancing and Settlement Code is the principal industry code that governs the seven-stage lifecycle from Stage 3 onward. It was first executed on 27 March 2001 alongside the New Electricity Trading Arrangements and now runs to over 1,800 pages of substantive text plus subsidiary documents (Code Subsidiary Documents, the Service Description and Service Description User Interface specifications, the Settlement Risk and Modelling documents). The BSC sets out who owes whom, on what basis, and how the calculation is performed. It is administered by BSCCo, a private company limited by guarantee that trades as Elexon, owned by its members (every BSC Party is a member) and recovers its costs through the BSC Charges levied on those parties.

The BSC modification that carries the consequential changes for Market-wide Half Hourly Settlement is P408.6 P408 was approved by Ofgem in November 2022 as the modification that defines the post-MHHS settlement run; it amends BSC Section S, the subsidiary Service Description and the Service Description User Interface to operate over half-hourly reads from the central settlement system for every Meter Point Administration Number, rather than the profiled non-half-hourly reads that were the pre-MHHS norm for the domestic population. P408 is the single most consequential BSC modification since the Code went live in 2001; it changes the unit of settlement from a profiled monthly read to a half-hourly read for around 33 million domestic MPANs, with the consequential data-volume change at the central settlement system from a few hundred million observations per day to around 1.6 billion observations per day at steady state.4

The BSC sits under the licence regime. Each licensee that participates in settlement (a generator, a supplier, a transmission owner, a distribution network operator, an interconnector operator) holds a licence granted by Ofgem under the Electricity Act 1989 and is bound by Standard Licence Conditions that include the obligation to comply with the BSC.5 The chain is: Electricity Act 1989 -- Ofgem licence -- Standard Licence Conditions -- BSC -- Code Subsidiary Documents -- daily settlement run. A reader who arrives wanting to know why a particular settlement-period number takes the value it does walks that chain in reverse to find the source rule.

Around 250 BSC Trading Parties sit inside the Code, across six categories: around 85 suppliers (domestic and non-domestic), around 80 generators (active Balancing Mechanism Units on the transmission system), around 50 traders, the 14 distribution licensees, the 3 transmission owners, and around 14 interconnector operators. Each Trading Party is bound to provide accurate metered data, to settle its imbalance position under the cash-out rules, and to post credit cover with the BSC Funds Administration Agent that backs the cash leg of every settlement-period transaction. The 250-party count has been broadly stable since 2020; the supplier count fluctuates with market entries and supplier-of-last-resort transfers, and the generator count is rising with the new-build pipeline that the Connections Reform Gate 2 outcomes published in April 2026 progressed through the connections queue.

NESO is not a BSC Trading Party. NESO is the System Operator under a separate transmission licence and interacts with the BSC by issuing Bid-Offer Acceptances to BMUs through the Balancing Mechanism; the accepted volumes and the resulting system price feed the settlement run. NESO also publishes the operational data through the Insights Solution and IRIS streaming endpoint that the rest of the market reads, including the half-hour system price (System Buy Price and System Sell Price) that the cash-out calculation in Stage 4 produces.2

Stage 1: measurement at the SMETS2 meter and the half-hourly observation

The lifecycle begins at the meter on the wall. A SMETS2 electricity meter (the second-generation specification under the Smart Energy Code) records active import energy at the close of each half-hour and stores the observation in volatile memory along with the half-hour identifier (the settlement period number from 1 to 48 on a normal day, 1 to 50 on the long clock-change day in October and 1 to 46 on the short clock-change day in March, plus the trading date). The meter signs the observation under its device certificate (issued by an Issuing Certificate Authority under the Smart Metering Key Infrastructure, with the SMKI Root operated by the DCC); the signature lets any downstream party verify that the observation originated at this specific meter and has not been altered in transit.

Around 35.9 million domestic and small non-domestic electricity and gas meters were in the field at the end of 2025 across Great Britain, of which around 33 million are SMETS2. The remaining few million are SMETS1 (the first-generation specification, migrated to the DCC infrastructure between 2018 and 2023 so they appear as SMETS2 from the DCC user perspective) or Advanced Metering Infrastructure on the non-domestic estate. The estate produces around 1.6 billion half-hourly observations per day after MHHS cutover in July 2027.4

The Communications Hub mounted next to the meter is the bridge between the Home Area Network (a Zigbee mesh at 2.4 gigahertz or 868 megahertz that carries traffic between the meter and the Hub) and the Wide Area Network (the cellular bearer carrying traffic between the Hub and the DCC Data Service Provider). The Hub is owned and operated by the DCC; the Communications Service Provider for the relevant region (Arqiva runs the UHF network in the North; Virgin Media O2 runs the cellular network across Central and South) carries the encrypted payload over the WAN. The Hub does not aggregate, summarise or enrich the observation; it is a transparent forwarder. The cryptographic chain runs end to end from the meter to the DCC Data Service Provider, not from the meter to the Hub, which is why a swap of a Communications Hub does not require a swap of the meter and the SMKI device certificate stays with the meter.

The DCC Data Service Provider, run by Capgemini under the DCC licence held by Capita, is the brain of the DCC core. Every DCC User Interface Specification (DUIS) request from a supplier, a distribution network operator or another authorised user lands at the Data Service Provider, is checked against the user's Service Request Permission set, is signed-validated against SMKI, is translated into one or more Great Britain Companion Specification (GBCS) commands, and is dispatched to the correct Communications Hub via the correct Communications Service Provider. Responses follow the reverse path. The DUIS is the only protocol a DCC user speaks; the user does not see GBCS, does not see Zigbee, does not see the cellular bearer, and does not see the meter manufacturer. From the user perspective the DCC presents a single uniform application programming interface for the entire 35 million meter estate.

The Energy Smart Data and Privacy Framework, published by DESNZ in March 2026, is the policy framework that defines how the consumer authorises a third party (a price-comparison service, a tariff-switching service, an advice service) to read this same observation under the Smart Data scheme that the Data (Use and Access) Act 2025 enables.7 The third party does not see the raw GBCS-signed observation; the third party sees a derived view that the supplier or another authorised intermediary publishes under the framework's data-handling rules, with the consumer's explicit consent on record.

The single observation that leaves the meter at the close of a half-hour is therefore a structured record containing the meter identifier, the trading date, the settlement period number, the active import register value in watt-hours (or in kilowatt-hours for some register variants), and the device signature. The downstream stages of the lifecycle read this record as the canonical truth of what the meter measured during the half-hour; every subsequent step refines, aggregates or substitutes the observation, but never amends the raw observation itself, which is preserved with its signature for the audit trail.

Stage 2: validation of the reading at the supplier and the central settlement system

The supplier ingests the half-hourly observation into its billing engine and runs the standard validation, estimation and substitution rules. Validation checks include: the observation arrived within the expected window (typically 24 to 36 hours after the trading day); the meter identifier matches a Meter Point Administration Number on the supplier's portfolio; the register value is monotonically non-decreasing (active import is a cumulative register, so a half-hour consumption is computed by differencing two consecutive register reads); the signature verifies against the meter device certificate; the settlement period number is within the valid range for the trading date.

Where validation succeeds, the observation is committed to the supplier's settlement store and is ready for Stage 3 aggregation. Where validation fails (typically because the observation has not arrived, because two consecutive register reads bracket a meter exchange event, or because the signature does not verify), the supplier applies a substitution. The substitution rule depends on the settlement regime: under the pre-MHHS Non-Half-Hourly regime, the substitution applies a Profile Class assumption that maps the daily total to a national-average half-hour shape; under MHHS, the substitution applies a per-meter estimation based on the same MPAN's reads from preceding trading dates with the same day-of-week and weather profile.

The estimated reads resolve to actual reads over the following weeks as the supplier receives delayed observations, resolves bracket reads and corrects signature failures. The volumetric correction from the estimated to the actual position is the dominant change between successive settlement runs at Stage 5; each reconciliation run replaces a slice of the estimated population with the actual reads and recomputes the cash position. The typical pattern for the domestic population in May 2026 is that around 99.7 percent of observations are validated and committed by Settlement Final (D plus 14 working days), around 99.95 percent are committed by R1 (D plus 24 working days) and the remainder resolves between R2 and R3.

The validation at the supplier is the first of two validation layers. The second layer runs at the central settlement system, where the same observation (now aggregated to the Grid Supply Point Group level under Stage 3) is checked against the supplier's submitted aggregated meter data, against the supplier's contracted position (declared through the Energy Contract Volume Notification flow under the BSC), and against the published demand profile for the GSP Group. A mismatch at the central settlement system triggers a dispute flow back to the supplier; the supplier resolves the dispute by re-submitting corrected aggregated data or by acknowledging the central position. The dispute flow is the source of the small percentage adjustments at R2.

BSC P408 amends the Service Description User Interface to operate over the canonical MHHS data format rather than the pre-MHHS aggregated profile format.6 The supplier-side validation under MHHS reads the raw half-hourly observations from the central settlement system rather than from the supplier's own ingestion pipeline; the supplier and the central settlement system therefore validate against the same source data, which removes one of the historical sources of dispute between the two views. The change is significant for any analyst tracking the dispute volume across the MHHS migration: the pre-MHHS dispute volume reflects the gap between two independent data pipelines, while the post-MHHS dispute volume reflects only the gap between two independent computations on the same data.

Stage 3: aggregation to the Grid Supply Point Group under the BSC

The half-hourly observation does not settle at the Meter Point Administration Number level. It settles at the Grid Supply Point Group level, where it is aggregated across every MPAN that the supplier serves within the Group, and is uplifted by the Line Loss Factor Class that applies to the MPAN's connection voltage. The Grid Supply Point is the boundary between the transmission system and the distribution system; the Group is the cluster of GSPs that the Balancing and Settlement Code treats as a single zone for settlement purposes. There are 14 GSP Groups across Great Britain, broadly matching the 14 distribution licence areas (one for each of the six DNO groups, with three Scottish Power and three SSEN areas plus the single areas for Northern Powergrid, Western Power Distribution, UK Power Networks and Electricity North West).

The Line Loss Factor Class applies a percentage uplift to the meter reading to reflect the energy lost on the distribution network between the GSP boundary and the meter on the wall. The uplift is a function of the connection voltage: a low-voltage domestic connection (LLFC class 01 across most DNOs) attracts an uplift of around 5 percent; a medium-voltage 11 kilovolt connection attracts an uplift of around 2 percent; a high-voltage 132 kilovolt connection attracts an uplift of around 0.5 percent. The LLFC table is published by each DNO and updated annually. A 1.47 kilowatt-hour meter read at LLFC class 01 becomes approximately 1.55 kilowatt-hours at the GSP boundary after the typical low-voltage uplift is applied.

The aggregation happens at the supplier and at the central settlement system. The supplier aggregates its own MPANs within each GSP Group into a single aggregated profile per Group per settlement period, and submits that profile to the central settlement system through the BSC P0244 D-flow (or the equivalent post-MHHS canonical flow under BSC P408). The central settlement system aggregates across all suppliers within each GSP Group to produce the Group-level demand profile that feeds the system-wide settlement calculation in Stage 4.

The data format for the aggregated profile is the BSC Data Transfer Catalogue (DTC) D-flow set. Each D-flow has a numeric identifier (D0001, D0036, D0086 and so on, plus P-flow identifiers for some BSC P-codes such as P0244), a defined sender, receiver, schema and purpose. The half-hourly profile flow has multiple variants depending on whether the meter is in Half-Hourly settlement (HHSP variant), Non-Half-Hourly settlement on the way to MHHS (NHHSP variant), or migrated to MHHS (canonical MHHS variant under BSC P408). After Milestone M15 in May 2027 every settlement period for every meter point is carried by the same canonical aggregated MHHS flow; the legacy variants are retired at Milestone M16 in July 2027.6

The aggregation step is also where the Embedded Generation Capacity that sits inside the GSP Group is netted against the gross demand. A solar PV installation on a domestic roof exports surplus generation back to the LV network; the export is metered through a separate active export register on the same SMETS2 meter, and is treated as a credit against the Group-level demand profile. The net Group demand is the gross demand minus the embedded generation export. The pattern matters more in 2026 than it did in 2024 because the domestic PV fleet has grown materially over the last twenty-four months (driven by the Capacity Market T-4 result that pulled forward new-build storage and by the Connections Reform Gate 2 outcomes that progressed 283 gigawatts of generation and storage to firm offers in April 2026).3

The aggregated Group-level profile that lands at the central settlement system is the canonical input to Stage 4. From this point on, the lifecycle is no longer tracking the single half-hourly observation at the meter on the wall; it is tracking the aggregated demand profile that the supplier presents to the central settlement system for cash-out purposes. The single observation is preserved in the audit trail (at the meter, at the DCC store, at the supplier and at the central settlement system), but the cash-out arithmetic operates on the aggregated profile.

Stage 4: settlement under BSC P408 and the half-hourly cash-out

The central settlement system runs the half-hourly cash-out under BSC Section S. For each settlement period, the system computes the system imbalance volume (the gap between metered demand and contracted demand summed across all suppliers, plus the gap between metered generation and contracted generation summed across all generators, plus the cross-border flows on the interconnectors). The system imbalance volume is the volume of energy that NESO had to procure through the Balancing Mechanism to keep the system balanced during the half-hour. The cash-out applies a single system price to every imbalance position in the half-hour: the System Buy Price (SBP) for parties that were short of energy (consumed more than they contracted to consume) and the System Sell Price (SSP) for parties that were long of energy (generated more than they contracted to generate).

The system price under the current single-price cash-out regime is the most expensive megawatt-hour of accepted Balancing Mechanism action in the settlement period (PAR1, after the change from PAR50 in 2018 under BSC modification P305 and the subsequent move to PAR1 under modification P371 in 2020). The PAR (price-averaging reference) of 1 megawatt-hour means the cash-out price reflects the marginal cost of the most expensive action NESO had to take to balance the system; parties that were short during the half-hour pay the full marginal price, and parties that were long receive the full marginal price. The single-price regime replaced the earlier dual-price regime in November 2015 under BSC modification P305 and was the most consequential price-formation change since the Code went live.

The system price lands on the Insights Solution and the IRIS streaming endpoint after each settlement run; the price is available to any market participant or analyst on a near-real-time basis after the Initial Information run on D plus 1 working day.2 Modo Energy, Cornwall Insight, EnAppSys and the academic data portals (UK Energy Research Centre at Imperial College, University of Sheffield, University of Birmingham) all run analytical layers on top of the IRIS feed; the page citations in this workspace that resolve to a half-hour balancing number trace back to IRIS as the primary source.

BSC P408 is the modification that holds the post-MHHS settlement step together.6 The change at the settlement step is principally one of granularity: the pre-MHHS settlement for the domestic population aggregated daily reads to a profiled half-hour shape (the Profile Class assumption); the post-MHHS settlement reads actual half-hourly reads for every MPAN. The change in granularity removes the dampening effect that Profile Class settlement applied to flexibility revenue. A household running a heat pump at 03:00 to take advantage of an overnight Time of Use rate appears in the post-MHHS settlement as actual consumption at 03:00; in the pre-MHHS settlement the consumption appears spread across the day under the Profile Class shape. The Electricity Networks Strategic Framework analysis placed cumulative consumer-led flexibility infrastructure savings from MHHS at forty to fifty billion pounds across 2021 to 2050.4

The cash position per BSC Party per settlement period is the output of Stage 4. The cash position is the product of the imbalance volume and the system price, with the sign convention that a party short of energy owes money (a payment from the party to the central settlement system) and a party long of energy is owed money (a receipt from the central settlement system to the party). The cash leg is settled through the BSC Funds Administration Agent at agreed cash-flow points; the FAA aggregates the per-party positions across the BSC modification cycle and instructs the BACS direct debit and credit transfers that move money between the BSC Parties and the central settlement account.

The credit cover that each BSC Party posts with the FAA is sized to the maximum cumulative cash exposure that the party can run up between two FAA settlement points; a supplier that is repeatedly short during a high-system-price half-hour cluster (a winter peak with a wholesale price spike) can run up a material cumulative position over the days between FAA settlement points, and the credit cover ensures that the FAA can clear the position even if the supplier becomes unable to meet its obligation. The credit-cover regime is the principal protection against a supplier default; the supplier-of-last-resort mechanism that follows a supplier default is described in Stage 7.

Stage 5: the SF, R1, R2, R3 and RF reconciliation timetable

Settlement is not a single event. It is a sequence of runs across fourteen calendar months, each pulling in more complete metered data and recalculating the cash position for every BSC Trading Party. The runs are: Initial Information (II) at one working day after the trading day; Settlement Final (SF) at fourteen working days; First Reconciliation (R1) at twenty-four working days; Second Reconciliation (R2) at forty-four working days; Third Reconciliation (R3) at eighty-seven working days; Final Reconciliation (RF) at fourteen calendar months. RF is the run that freezes the books; no further settlement adjustment is possible after RF lands.4

The reason the timetable extends across fourteen months is data quality. Three things change between runs. Estimates resolve into actuals as more meter readings arrive (especially for the legacy non-half-hourly population that MHHS is replacing). Settlement-period adjustments and corrections work through the system as suppliers and the central settlement system resolve disputes. And volumes for embedded generation, EV chargers, asset-backed contracts and Balancing Mechanism actions resolve over the months following the trading day. Each reconciliation run shrinks the band of estimation; RF is the moment when no more correction is possible.

RunTimingPurposeTypical change against the prior run
IID + 1 working dayFirst operational view of the day; missing reads heavily estimatedNot applicable; first run
SFD + 14 working daysFirst binding cash position; most reads validatedLarger; first invoiceable cash
R1D + 24 working daysMost half-hourly data now arrivedSmall percentage adjustments
R2D + 44 working daysDisputes and embedded generation resolvedSmaller still
R3D + 87 working daysLong-tail metering data resolvedMarginal
RFD + 14 calendar monthsFinal closing of the books; never reopenedFinal fix; books frozen

The cash flow per BSC Trading Party follows the run cadence. The II run produces an indicative position that has no contractual force; the SF run produces the first invoiceable position and triggers the first cash leg through the Funds Administration Agent. R1, R2 and R3 each produce an incremental cash adjustment as the position resolves; the cumulative adjustment from SF to R3 is typically less than half a percent for a major supplier with a well-validated meter base, and can be larger for a smaller supplier with a higher estimated-read proportion at SF. RF produces the final cash leg and locks the position.

The two clocks in the timetable matter for any analyst tracking the settlement state. The working-day clock (II at D plus 1 working day through R3 at D plus 87 working days) reflects the operational cadence of the central settlement system, the supplier dispute resolution and the meter-read arrival; the calendar-month clock (RF at D plus 14 calendar months) reflects the statutory closure date that the BSC sets for the trading day. The two clocks diverge: a trading day in January typically reaches RF in March of the following year, and a trading day in December typically reaches RF in February of the following year, because the working-day count is paused by bank holidays and the calendar-month count is not.

BSC P408 amends the Service Description to operate the same five-run timetable over the post-MHHS data, with the same working-day cadence and the same fourteen-calendar-month RF clock.6 The substantive change at the reconciliation step is the percentage adjustment between SF and the subsequent runs: the post-MHHS data has a higher initial validated-read percentage (because every MPAN reports half-hourly observations directly rather than relying on the Profile Class estimation), so the cumulative SF-to-RF adjustment for the domestic population shrinks materially. The pre-MHHS Profile Class regime typically saw the largest single-run adjustment at R1 (when the actual non-half-hourly reads arrived and replaced the Profile Class estimate); the post-MHHS regime sees a much smaller R1 adjustment because the half-hourly observations are already in the system at II.

The legacy Initial Information run is not labelled as a separate cash leg in the BSC; II is an operational view, not a binding settlement. The settlement run timetable that produces cash legs is therefore SF, R1, R2, R3 and RF; the II run sits above them as the operational visibility that the market reads through the Insights Solution and IRIS on D plus 1 working day. Some references in the older Code documentation use a four-run shorthand (R1 through RF), which corresponds to the four cash-leg-producing runs after SF; this workspace uses the five-run convention (SF through RF) so the SF cash leg is named explicitly.

Stage 6: the supplier bill and its component structure under the Default Tariff Cap

The consumer bill is the visible end of the lifecycle and the artefact that any consumer reads. The bill shows the energy charge (computed from the tariff and the metered consumption), the standing charge (a daily fixed amount), the network charges that the supplier passes through from the Distribution Use of System (DUoS) and Transmission Network Use of System (TNUoS) tariffs published by the DNO and the TO, the Renewables Obligation pass-through, the Climate Change Levy on non-domestic supplies, VAT at 5 percent on the domestic supply, and any standing charge variations under the prepayment regime.

The Default Tariff Cap published by Ofgem on a quarterly cadence sets the ceiling that the supplier can charge a household on the standard variable tariff. The Q2 2026 cap effective from 1 April 2026 is one thousand six hundred and forty one pounds per year for a typical dual-fuel direct debit household, down six point six percent against the Q1 2026 cap of one thousand seven hundred and fifty eight pounds, after wholesale gas prices fell through Q1 2026.8 The cap decomposes into five components: wholesale, network, policy, operating, and margin. Each component is the output of a different lifecycle stage and a different market segment.

ComponentShare of capSource lifecycle stageWhat it recovers
Wholesale~34 percentStage 4 settlement under BSC P408Supplier's actual wholesale energy cost across the cap period
Network~22 percentStage 3 aggregation at the GSP GroupDUoS and TNUoS charges plus BSUoS recovery
Policy~16 percentStages 4 and 6 (policy pass-through)Renewables Obligation, FiT, CfD, CM levy, ECO obligations
Operating~17 percentStages 1 through 6 (supplier operating cost)Metering, billing, customer service, bad debt allowance
Margin~5 percentStage 6 supplier marginSupplier earnings before tax
VAT 5 percent~5 percentStage 6 statutory add-onValue Added Tax on the domestic supply

The cap is the quarterly ceiling, not the price the consumer pays. A consumer on a fixed-term deal pays the price set by the supplier when the deal was agreed; a consumer on the standard variable tariff pays the cap, computed at the consumer's actual consumption rather than at the typical-household reference. The cap methodology assumes a specific consumption pattern (a typical household consuming 2,700 kilowatt-hours of electricity and 11,500 kilowatt-hours of gas per year on the medium-consumption reference, with a typical day-night split for the dual-rate variant) and recomputes for each consumer's actual consumption.

The wholesale component recovers the supplier's actual wholesale cost across the cap period, with the hedge cover the supplier has placed against the period determining how exposed the supplier is to spot moves. Ofgem's cap methodology assumes a specific hedge timetable (rolling forward purchases over an eight-month window ahead of each cap period) and prices the wholesale component against that assumed book; a supplier that has hedged differently bears or benefits from the gap between its actual book and the cap methodology assumption. The wholesale component fell sharply between Q1 2026 and Q2 2026 because the cap-window wholesale prices fell through the Q1 2026 hedging window.8

The network component recovers the DUoS and TNUoS charges that the supplier passes through, plus the BSUoS recovery that NESO levies on suppliers for the operational cost of balancing the system. The DUoS tariffs are published by each DNO annually under the price-control framework that Ofgem currently runs as RIIO-ED2 for 2023 to 2028; the TNUoS tariffs are published by NESO annually under the CUSC charging methodology. The BSUoS recovery moved from a half-hourly volumetric charge to a fixed-payments-per-half-hour basis under the BSUoS reform that went live on 1 April 2023.

The policy component recovers the cost of the obligations that DESNZ levies on suppliers to fund the Renewables Obligation, the Feed-in Tariff legacy book, the Contracts for Difference scheme that the Low Carbon Contracts Company administers, the Capacity Market levy that EMR Settlement Limited administers, and the Energy Company Obligation that funds the Warm Homes Plan and the related fuel-poverty measures. Each obligation has its own settlement engine (LCCC for CfD, EMRS for CM, supplier for ECO) and its own cash leg back to the supplier; the policy component on the consumer bill is the aggregated pass-through of those obligations.

The operating component recovers the supplier's metering, billing, customer service and bad-debt allowance costs. The bad-debt allowance is a material component of the operating share; it covers consumers who default on their bill and is the principal route through which the cost of supplier failure is socialised across the consumer base under the supplier-of-last-resort mechanism. The margin component is the supplier's earnings before tax under the cap; it is small in absolute terms (around 5 percent of the cap) and is the regulated return that justifies the supplier's risk-bearing position between Stage 4 settlement and Stage 7 payment.

Stage 7: payment, direct debit and the supplier-of-last-resort backstop

The consumer pays the supplier through one of three channels: direct debit (the dominant channel for around 70 percent of domestic accounts; the consumer authorises the supplier to draw a fixed monthly amount from the consumer's bank account, with the amount reviewed annually or more frequently against actual consumption); standing order or pay-on-receipt-of-bill (a smaller share, for consumers who prefer to manage the cash flow themselves); and prepayment top-up (for consumers on prepayment meters who top up at a Post Office, online or at a corner-shop terminal). The direct debit channel is the cheapest for the supplier (lower bad-debt allowance, lower customer-service cost) and is reflected in the cap methodology with a small discount against the standard credit tariff.

The supplier holds the cash flow between Stage 4 settlement and Stage 7 payment. Settlement under BSC P408 produces the supplier's cash position at the central settlement system as the half-hour transactions resolve; the supplier pays the central settlement system through the Funds Administration Agent on the BSC cash-leg cadence (SF, R1, R2, R3 and RF), while the consumer pays the supplier on the supplier's billing cadence (typically monthly by direct debit). The supplier's working capital position absorbs the timing gap.

The credit-cover regime at the BSC backs the supplier's cash leg. Each BSC Trading Party posts credit cover with the Funds Administration Agent sized to the maximum cumulative cash exposure the party can run up between two FAA settlement points; the FAA can clear the position even if the supplier becomes unable to meet its obligation. The credit cover is the first line of defence against a supplier default.

The supplier-of-last-resort mechanism is the second line of defence. When Ofgem determines that a supplier can no longer meet its obligations to consumers (typically because the supplier is in administration or has had its licence revoked), Ofgem appoints another supplier as the supplier of last resort for the failing supplier's consumer book; the SoLR takes on the failing supplier's consumers and continues to supply them under the same regulated cap (or under the SoLR's own tariff if the consumers were on a fixed-term deal that the SoLR honours). The cost of taking on the failing supplier's book (the credit balances the failing supplier owed consumers, the operating cost of onboarding the consumer base, the bad-debt cost on the failing supplier's account ledger) is recovered through a SoLR levy on all suppliers, which the suppliers pass through to all consumers through the bad-debt allowance in the cap operating component.

The SoLR mechanism was invoked extensively across 2021 and 2022 during the European wholesale gas price spike; 29 suppliers exited the market between September 2021 and June 2022, and SoLR transfers moved around 2.4 million consumer accounts to other supply companies. The cumulative SoLR cost across that period was around 2.7 billion pounds, recovered through the consumer cap over the subsequent two cap windows.8 The mechanism is the principal route through which the cost of a market exit is socialised across the consumer base; it is the structural reason that the cap operating component carries the bad-debt allowance it does.

The consumer's actual payment closes the lifecycle. From the moment the consumer's bank executes the direct debit (typically a fixed date in the month, with the supplier's bank account on the receiving leg), the cash has moved from the consumer to the supplier and the lifecycle for the consumed half-hour is materially complete. The corresponding cash legs at the central settlement system close progressively at SF, R1, R2, R3 and RF; the RF run at fourteen calendar months after the trading day is the final close.

The MHHS programme: 1.6 billion observations a day after cutover in July 2027

The Market-wide Half Hourly Settlement programme is the largest single change to the lifecycle since the New Electricity Trading Arrangements went live on 27 March 2001. The Ofgem decision to mandate the move was published in April 2021; the legal mechanism is BSC modification P408, which carries the consequential changes to the Balancing and Settlement Code and to its subsidiary documents. Elexon was appointed Implementation Manager in 2022 and operates a numbered milestone framework from M1 through M16. The operational migration window started on 22 October 2025 (Milestone M11) and runs to cutover at Milestone M16 in July 2027.4 6

MilestoneDateRequired state
M1122 October 2025Operational Go-live; central MHHS systems live; first parties cutover begins
M11 + 4 months16 February 2026At least 2 million MPANs settled under MHHS
M12February to April 2026Data Integration Platform stable; first wave of suppliers migrated
M13May to August 2026Mid-wave migrations; legacy reporting reduced; 10 million MPANs initiated
M14October 2026Around 80 percent of MPANs migrated to MHHS
M15May 2027Full Implementation Date; all MPANs in MHHS scope
M16July 2027Cutover complete; legacy non-half-hourly systems retired

The data-volume change is the headline operational consequence. The pre-MHHS central settlement system processes a few hundred million observations per day (the half-hourly observations from the Time of Use minority plus the profiled daily reads from the Profile Class population). The post-MHHS central settlement system processes around 1.6 billion observations per day at steady state (33 million domestic MPANs each producing 48 half-hourly observations per day, plus the existing non-domestic Half-Hourly population). The annual volume after cutover is around 583 billion observations per year flowing through the settlement chain. Elexon's MHHS Programme reporting places the steady-state target at around 500 billion half-hourly observations per year.4

The economic effect of MHHS is to remove the price-dampening that Profile Class settlement applied to flexibility revenue. A household running a heat pump at 03:00 to take advantage of an overnight Time of Use rate appears in the post-MHHS settlement as actual consumption at 03:00; in the pre-MHHS settlement the consumption appears spread across the day under the Profile Class shape. The Electricity Networks Strategic Framework analysis placed cumulative consumer-led flexibility infrastructure savings from MHHS at forty to fifty billion pounds across 2021 to 2050. The savings come through three channels: lower peak procurement (fewer peak-hour megawatts the network has to build), lower network reinforcement (more efficient use of the existing wires), and lower wholesale cost (suppliers can buy more accurately against actual half-hourly demand).

The MHHS migration runs supplier by supplier and MPAN cohort by MPAN cohort. By 16 February 2026 over 2 million MPANs were settled under MHHS (Milestone M11 + 4 months target); by mid-quarter Q1 2026 ten million MPAN initiations were complete across Milestones M10 to M13. The migration cadence accelerates through M13 and M14 as the first-wave suppliers complete migration and the second-wave suppliers begin theirs; the Full Implementation Date at M15 in May 2027 sees all MPANs in scope, and the M16 cutover in July 2027 retires the legacy non-half-hourly systems.

The supplier-side preparation for MHHS includes the move from the BSC P0244 D-flow to the canonical post-MHHS aggregated MHHS flow under BSC P408, the update to the supplier's billing engine to consume half-hourly reads for every MPAN rather than profiled daily reads for the non-Time-of-Use population, and the update to the supplier's customer-facing systems to present half-hourly consumption data and Time of Use tariff variants to the consumer. The Energy Smart Data and Privacy Framework that DESNZ published in March 2026 provides the consumer-side counterpart: with MHHS data available for every meter, the framework defines how a consumer authorises a third party to read that data under the Smart Data scheme.

The MHHS programme is independent of the Reformed National Pricing decision under REMA Phase 2. The two are interlocked: MHHS produces the half-hourly settlement data that Reformed National Pricing operates over; the SSEP and CSNP that REMA Phase 2 introduced as the strategic-planning artefacts consume the half-hourly data that MHHS produces as one of the input datasets. A reader who arrives wanting to know whether MHHS is on track in the May 2026 update should read the Milestones M10 to M13 attainment (ten million MPANs initiated) as the principal signal; the M14 attainment in October 2026 (around 80 percent of MPANs migrated) is the next checkpoint.

Worked example: a 1,200 kWh per month household on a Time of Use tariff in Q2 2026

A single representative household runs through the seven stages with real Q2 2026 numbers, so the lifecycle is grounded in something specific that a reader can recompute against the Default Tariff Cap. The household consumes 1,200 kilowatt-hours per month of electricity (which is around 14,400 kilowatt-hours per year, somewhat above the medium-consumption reference of 2,700 kilowatt-hours that the Q2 2026 cap uses; the 1,200 per month figure reflects an all-electric household with a heat pump and an electric vehicle, which is the pattern the post-2035 net-zero target points toward). The household is on a three-rate Time of Use tariff with a peak rate (17:00 to 19:00), a standard rate (08:00 to 17:00 and 19:00 to 22:00) and an off-peak rate (22:00 to 08:00); the load shape is 12 percent peak, 46 percent standard, 42 percent off-peak.

Stage 1: measurement at the meter

The SMETS2 meter records 48 half-hourly active import observations per day, for 30 days per month, giving 1,440 observations per month. The monthly total is 1,200 kilowatt-hours, so the average per-observation consumption is 0.833 kilowatt-hours.

Monthly consumption = 1,200 kWh

Observations per month = 48 / day · 30 days = 1,440 observations

Average per observation = 1,200 / 1,440 = 0.833 kWh per half-hour

The peak-hour observations (settlement periods 35 to 38, covering 17:00 to 19:00) carry 12 percent of the monthly total spread across four periods per day; that is 144 kilowatt-hours per month across 120 peak observations, or 1.20 kilowatt-hours per peak observation. The off-peak observations (settlement periods 45 to 48 and 1 to 16, covering 22:00 to 08:00) carry 42 percent of the total spread across twenty periods per day; that is 504 kilowatt-hours per month across 600 off-peak observations, or 0.840 kilowatt-hours per off-peak observation.

Stage 2: validation at the supplier

The supplier ingests the 1,440 monthly observations into its billing engine over the following 24 to 36 hours. Around 99.7 percent of the observations validate at the first pass; 4 to 5 observations per month fail the first-pass validation (typically because the cellular bearer suffered a transient outage and the observation arrived late). The supplier applies a per-meter substitution to the failed observations, based on the same MPAN's reads from the preceding 14 days under MHHS rules; the substitution is corrected to the actual value at R1 (D plus 24 working days) as the late-arriving observations reach the central settlement system.

Observations validated at first pass = 1,440 · 0.997 = 1,436 observations

Observations substituted at first pass = 1,440 - 1,436 = 4 observations

The four substituted observations carry an aggregate consumption of around 3.3 kilowatt-hours, against the monthly total of 1,200 kilowatt-hours; the percentage exposure to substitution at SF is 0.28 percent. By R1 the substitution resolves to actuals and the exposure drops to zero.

Stage 3: aggregation to the Grid Supply Point Group

The supplier aggregates the household's 1,440 observations across the supplier's MPAN portfolio within the same GSP Group, and applies the Line Loss Factor Class uplift. The household connects at LLFC class 01 (low-voltage domestic), with a typical uplift of around 5 percent; the aggregated monthly consumption at the GSP boundary is 1,260 kilowatt-hours.

Aggregated consumption at GSP = 1,200 · 1.05 = 1,260 kWh per month

The supplier submits the aggregated profile to the central settlement system through the canonical post-MHHS aggregated MHHS flow under BSC P408 (or through the legacy BSC P0244 D-flow if the household sits on an MPAN that has not yet migrated to MHHS; the worked example assumes the household has migrated, which is consistent with the Milestone M12 cohort that the supplier brings online during Q2 2026).

Stage 4: settlement under BSC P408

The central settlement system runs the half-hourly cash-out under BSC Section S. For each settlement period, the system computes the supplier's imbalance volume (the gap between metered demand and contracted demand) and applies the System Buy Price or System Sell Price to compute the cash position. The household's contribution to the supplier's settlement position is the household's actual consumption, which the supplier has hedged through forward purchases under the eight-month hedge window that the Default Tariff Cap methodology assumes.

The cap-window wholesale cost component for Q2 2026 is approximately 17.4 pence per kilowatt-hour at the cap reference. For the household consuming 1,200 kilowatt-hours per month, the wholesale recovery share of the bill is:

Wholesale recovery = 1,200 · 0.174 = £208.80 per month

That is the wholesale share at the cap reference consumption; the household's actual wholesale exposure (the gap between the contracted hedge and the cleared cash-out price for each half-hour) is settled through the BSC under the supplier's settlement account, not on the household's bill. The household sees only the cap-determined wholesale rate.

Stage 5: reconciliation across SF, R1, R2, R3 and RF

The SF cash leg at D plus 14 working days fixes the first invoiceable position. For the household's MPAN this is essentially the actual consumption (because 99.7 percent of the observations validated at first pass and the 0.28 percent estimated share resolves by R1). The cumulative SF-to-RF adjustment for the household contribution is therefore around 0.3 percent of the monthly consumption.

SF position = 1,200 kWh per month

R1 adjustment = +3.3 kWh (0.28 percent)

R2 adjustment = +0.2 kWh (0.02 percent)

R3 adjustment = 0 kWh (negligible)

RF locks at D + 14 calendar months: 1,203.5 kWh per month

The household does not see the reconciliation arithmetic on the bill; the supplier absorbs the small SF-to-RF adjustment in its operating allowance under the cap. The reconciliation is visible only at the supplier's settlement account at the central settlement system.

Stage 6: the supplier bill under the Q2 2026 cap

The supplier issues the bill to the household on a monthly cadence. The Q2 2026 Default Tariff Cap effective from 1 April 2026 sets the ceiling at £1,641 per year for a typical dual-fuel direct debit household at the cap reference consumption (2,700 kWh electricity, 11,500 kWh gas).8 For the all-electric 1,200-kWh-per-month household, the cap-rate computation pro-rates the cap to the household's actual consumption.

The electricity-only share of the cap reference is approximately one third (the cap is for a typical dual-fuel household; the electricity-only share is around £540 per year at the reference consumption of 2,700 kWh electricity, or 20.0 pence per kWh blended rate plus a daily standing charge of around 50 pence).

Energy charge = 1,200 · 0.200 = £240.00 per month at the blended rate

The Time of Use tariff redistributes the energy charge across the three rate bands. With peak at 35 pence per kWh, standard at 24 pence per kWh and off-peak at 12 pence per kWh, the monthly energy charge for the 12-46-42 load shape is:

Peak share = 1,200 · 0.12 · 0.35 = £50.40

Standard share = 1,200 · 0.46 · 0.24 = £132.48

Off-peak share = 1,200 · 0.42 · 0.12 = £60.48

Total energy charge = £243.36 per month

Adding the standing charge of 50 pence per day across 30 days, the network pass-through, the policy pass-through and VAT at 5 percent on the domestic supply:

Standing charge = 30 · 0.50 = £15.00

Network and policy pass-through (estimated) = £75.00

VAT at 5 percent = (243.36 + 15.00 + 75.00) · 0.05 = £16.67

Total monthly bill = 243.36 + 15.00 + 75.00 + 16.67 = £350.03 per month

The annual bill for the 1,200-kWh-per-month all-electric household is around £4,200 per year. That is above the typical-household cap of £1,641 because the typical-household reference assumes a dual-fuel split with most heat coming from gas; the all-electric household pays more for electricity but does not pay for gas. The household's total energy spend (electricity only at £4,200) is comparable to the typical dual-fuel household's combined spend on electricity and gas (£1,641 at the reference consumption) after the gas component is removed.

Stage 7: payment by direct debit

The household pays the supplier by monthly direct debit at £350.03 per month. The supplier's bank account receives the direct debit on the agreed monthly date; the supplier's working capital position absorbs the timing gap between the household's monthly direct debit and the BSC cash legs at SF, R1, R2, R3 and RF.

If the supplier becomes unable to meet its obligations, Ofgem appoints a supplier of last resort under the SoLR mechanism; the SoLR takes on the household's account and continues to supply at the same cap (or under the SoLR's own tariff if the household was on a fixed-term deal that the SoLR honours). The cost of the transfer is recovered through the SoLR levy on all suppliers, passed through the bad-debt allowance in the cap operating component, and ultimately socialised across the consumer base.

The lifecycle for the household's December 2026 consumption closes at the corresponding RF run at fourteen calendar months: February 2028. From the household's perspective the bill is settled the month after consumption; from the central settlement system's perspective the books for the December 2026 trading days are frozen in February 2028.

The worked example demonstrates that the seven-stage lifecycle is the same machinery for every household. The numbers scale linearly with consumption, the cap rate redistributes through the Time of Use shape, and the reconciliation arithmetic stays under 0.3 percent of the monthly consumption for a household with a well-validated meter. The Default Tariff Cap is the single regulatory ceiling that sits above the whole structure; the BSC P408 modification is the single rule that holds the settlement step together; the MHHS programme is the single migration that brings every meter into the half-hourly regime.

Primary sources

The most load-bearing sources are listed below.

  1. Final Auction Parameters T-1 and T-4 Capacity Market Auctions; DESNZ letter to NESO, February 2026. T-4 2029 to 2030 cleared at £27.10 per kilowatt year for 40.1 GW; T-1 2026 to 2027 cleared at £5.00 per kilowatt year for 7.2 GW. https://www.gov.uk/government/publications/capacity-market-auction-parameters-letter-from-desnz-to-neso-february-2026
  2. BMRS Insights Solution and IRIS API; Elexon, live since 31 May 2024 (replaced the legacy BMRS). The canonical primary source for half-hourly balancing-mechanism prices, accepted volumes, system price and operational data. https://bmrs.elexon.co.uk/
  3. NESO Data Portal; operational and planning data, including the Insights Solution and IRIS feeds that succeed the legacy BMRS, plus the Carbon Intensity API jointly with the University of Oxford. https://www.neso.energy/data-portal
  4. Market-wide Half Hourly Settlement Programme; Elexon. Migration began 22 October 2025 under Milestone M11; cutover Milestone M16 in July 2027; steady-state target around 500 billion half-hourly observations per year. https://www.elexon.co.uk/bsc/operational/market-wide-half-hourly-settlement/
  5. SLC 25 of the Electricity Distribution Licence; the standard licence condition that the BSC sits under. https://epr.ofgem.gov.uk/Content/Documents/Electricity Distribution Consolidated Standard Licence Conditions - Current Version.pdf
  6. BSC Modification P408; the BSC modification carrying the consequential changes for MHHS implementation; approved by Ofgem in November 2022. https://www.elexon.co.uk/mod-proposal/p408/
  7. Energy Smart Data and Privacy Framework; DESNZ, March 2026. The policy framework for the energy-smart-data scheme that the Data (Use and Access) Act 2025 enables. https://www.gov.uk/government/publications/energy-smart-data-and-privacy-framework
  8. Default Tariff Cap level quarterly determination; Ofgem. Q2 2026 (effective 1 April 2026): £1,641 per year typical dual-fuel direct debit, down 6.6 percent on Q1 2026's £1,758. https://www.ofgem.gov.uk/information-consumers/energy-advice-households/energy-price-cap

The Balancing and Settlement Code (current Issue at the date of review) and its Section S settlement provisions are cited inline as the principal source for the seven-stage lifecycle; BSC Section S is the substantive content that BSC P408 amends.