Where do the cables run?

Ten operational links connect GB to France, the Netherlands, Belgium, Norway, Denmark, and Ireland. Four more are under construction or planned. The map below shows each cable's landing points and rated capacity.

10.3 GW
operational capacity
10 links across 6 countries
~30%
of average demand
can be met by imports
6
countries connected
FR, NL, BE, NO, DK, IE
~18 GW
potential by 2030
with planned projects
GB interconnector cable map GB Ireland France Belgium Netherlands Norway Denmark Germany IFA 2 GW IFA2 1 GW ElecLink 1 GW Nemo 1 GW BritNed 1 GW NSL 1.4 GW Viking 1.4 GW Moyle 0.5 GW EWIC 0.5 GW Greenlink 0.5 GW NeuConnect 1.4 GW GridLink 1.4 GW Tarchon 1.4 GW LirIC 0.7 GW Operational Under construction Planned Capacity shown in GW

What does the interconnector portfolio look like?

Each link connects GB to a specific country via high-voltage direct current cables. They are owned and operated by a mix of transmission owners, independent developers, and joint ventures. All require an electricity interconnector licence from Ofgem.

Name Country Capacity Length Commissioned Status
IFAFrance2,000 MW70 km1986Operational
IFA2France1,000 MW240 km2021Operational
ElecLinkFrance1,000 MW51 km2022Operational
BritNedNetherlands1,000 MW260 km2011Operational
Nemo LinkBelgium1,000 MW140 km2019Operational
NSLNorway1,400 MW720 km2021Operational
Viking LinkDenmark1,400 MW765 km2023Operational
MoyleIreland (NI)500 MW63 km2001Operational
EWICIreland (RoI)500 MW261 km2012Operational
GreenlinkIreland (RoI)500 MW190 km2024Operational
NeuConnectGermany1,400 MW720 km~2028Construction
GridLinkFrance1,400 MW210 km~2028Planned
LirICIreland700 MW~260 km~2030Planned
TarchonGermany1,400 MW~620 km~2030Planned
Why does France have three separate links?

IFA was built in 1986 and remains the highest-capacity single link. IFA2 added diversity by landing at a different point on the south coast. ElecLink runs through the Channel Tunnel infrastructure, which gives it a distinctive cost and risk profile. Three separate cables to the same country reduces the chance that a single fault takes out all French interconnection at once.

What is the cap and floor regime?

Ofgem's cap and floor provides interconnector investors with a minimum revenue guarantee (the floor) and caps upside (the ceiling). If congestion revenues fall below the floor, consumers top up the difference. If revenues exceed the cap, the surplus is returned to consumers. This reduces investment risk while protecting consumers from excessive rents. Most new interconnectors since 2014 have been developed under this regime.

How do interconnectors actually work?

Electricity flows through interconnectors from the lower-priced market to the higher-priced market. When electricity is cheaper in France than GB, IFA imports French power. When GB has surplus wind pushing prices down, power flows the other way.

Capacity allocation

Interconnector capacity is sold through explicit auctions (annual, seasonal, monthly, daily, and intraday) run by the Joint Allocation Office. Traders bid for the right to flow power in a specific direction at a specific time. Since Brexit, GB is no longer part of the EU's coupled day-ahead market, which makes allocation less efficient than it was.

Revenue model

Interconnector owners earn revenue from the spread between wholesale prices in the two connected markets. When the price difference is large, revenues are high. When prices converge, revenues fall. The cap and floor regime smooths this for most newer links.

System security

NESO treats interconnectors as both a supply source and a contingency risk. If a 2 GW link trips during high import, the system loses a large block of power instantly. NESO must hold sufficient reserve to cover the largest single loss, and the cost of that reserve is factored into balancing costs.

Post-Brexit trading

Before Brexit, GB participated in the EU's single day-ahead coupling mechanism, which optimised cross-border flows automatically. Since January 2021, GB has used explicit auctions instead. Ofgem estimated the efficiency loss at 17 to 38 million pounds per year. Discussions about multi-region loose volume coupling continue, but implementation remains incomplete.

What is the difference between HVDC and HVAC interconnection?

All long-distance subsea interconnectors use high-voltage direct current because AC cables generate reactive power over distance, which limits practical cable lengths to roughly 50 to 80 km without compensation. HVDC avoids this and allows precise control over power flow direction and magnitude. The converter stations at each end are expensive, but for cables longer than about 80 km the economics favour DC.

Can interconnectors provide frequency response?

Modern HVDC converters can provide synthetic inertia and frequency response services, which makes them more valuable than older links that simply transferred bulk energy. Viking Link and NSL both have technical capability to support GB frequency management, although the commercial and regulatory arrangements for these services are still maturing.

Why do interconnectors matter for Clean Power 2030?

The Clean Power 2030 plan relies on interconnectors to help balance a system with very high wind and solar penetration. When the wind is not blowing across north-west Europe, interconnectors can import from hydro-rich Norway or nuclear-heavy France. When GB has excess wind, they can export to avoid curtailment.

The diversity argument

Weather patterns across Europe are not perfectly correlated. When it is calm in the North Sea, it may be windy in the Bay of Biscay. When it is cold and still in GB, Norwegian hydro reservoirs may be full. The more interconnected GB is, the less domestic backup capacity is needed. But this creates a dependency on the political and market conditions of neighbouring countries.

The limits of import reliance

Interconnectors help, but they do not replace the need for domestic networks, firm capacity, or local flexibility. If GB itself is tight and so are its neighbours, imports will not materialise at any price. The planned pipeline adds about 5 GW, but not all projects will reach final investment decision.

Methodology and sources

Last reviewed: 17 March 2026

Content sourced from the React page component at commit e19c4d6. The cable map shows all operational and planned interconnectors with verified capacity figures. Supporting sections cover portfolio detail, market mechanics, and the Clean Power 2030 context.

SourceOfgem interconnectors — current interconnector estate and regulatory context.
SourceCap and floor handbook 2024 — investment framework and regulatory treatment.
SourceElexon BMRS — live flow data and system context.
SourceNESO ETYS — system planning and interconnector capacity projections.
Next route

Voltage: the stepping-down hierarchy

Follow the voltage cascade from 400 kV transmission to 230 V at your socket.